File #: R-2017-090    Version: 1 Name: Hazen & Sawyer Well Casing & FDEP Permit
Type: Resolution Status: Passed
File created: 3/15/2017 In control: Department of Public Utilities
On agenda: 4/5/2017 Final action: 4/5/2017
Title: A Resolution Of The City Commission Of The City Of Hollywood, Florida, Authorizing The Appropriate City Officials To Issue The Attached Amendment No. 1 To The Authorization To Proceed For Work Order No. H&S 17-01 Between Hazen And Sawyer P.C., And The City Of Hollywood To Provide Professional Engineering Services For Well Casing Cleaning And Operational Permit Renewal With The Florida Department Of Environmental Protection For The Two Deep Injection Wells At The Southern Regional Wastewater Treatment Plant, In An Amount Not To Exceed $69,404.00 (16-9938).
Attachments: 1. Resolution - Hazen & Sawyer Well Casing & FDEP Permit.pdf, 2. ATP Amend 1- Hazen & Sawyer Well Casing & FDEP Permit.pdf, 3. ATP - Hazen & Sawyer Well Casing & FDEP Permit.pdf, 4. Injection Well MIT Amendment 1 - Hazen & Sawyer Well Casing & FDEP Permit.pdf, 5. Term Sheet - Hazen & Sawyer Work Order H&S 17-01.pdf, 6. BIS 17139.pdf
Title
A Resolution Of The City Commission Of The City Of Hollywood, Florida, Authorizing The Appropriate City Officials To Issue The Attached Amendment No. 1 To The Authorization To Proceed For Work Order No. H&S 17-01 Between Hazen And Sawyer P.C., And The City Of Hollywood To Provide Professional Engineering Services For Well Casing Cleaning And Operational Permit Renewal With The Florida Department Of Environmental Protection For The Two Deep Injection Wells At The Southern Regional Wastewater Treatment Plant, In An Amount Not To Exceed $69,404.00 (16-9938).


Body

Staff Recommends: Approval of the attached Resolution


Explanation:
The two (2) existing Deep Injection Wells were placed in service in 2002 and are currently serving as the primary disposal method at the City of Hollywood - Southern Regional Wastewater Treatment Plant (SRWWTP) under FDEP Permit Number 156419-005-UO issued on September 28, 2012.

The FDEP Permit Number 156419-005-UO for the operation of the two existing Deep Injection Wells will expire on September 27, 2017 and operating permit renewal application needs to be prepared and submitted before the expiration date.

WWTP Operation staff noticed some level of back pressure increase in the two Deep Injection Wells after 15 years of continuous operation and suggested well casing cleaning be conducted under the ongoing Deep Injection Well Mechanical Integrity Testing (MIT) project.

Hazen and Sawyer, P.C. was authorized via the Authorization to Proceed for Work Order No. 17-01 on November 17, 2016 for an amount not to exceed $39,730.00 to provide professional engineering services related to design, bidding, and construction services for Deep Injection Well MIT project.

The City requested a proposal from Hazen and Sawyer, P.C. to provide Professional Engineering Services for the design and construction services related to well casing cleaning and operational permit renewal with FDEP for the two Deep Injection Wells.

Hazen and Sawyer, P.C...