Title
A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute A Contract With Youngquist Brothers, Inc. For Construction Services Related To Deep Injection Wells No. 3 And No. 4 Located At The Southern Regional Wastewater Treatment Plant, As Identified In The 2007/2008 Wastewater System Master Plan, In The Amount Of $39,939,939.00; Approving An Amendment To The Fiscal Year 2019 Operating Budget And Capital Improvement Plan.
Body
Staff Recommends: Approval of the attached Resolution.
Explanation:
The 2007/2008 Wastewater System Master Plan identified the need to meet new regulatory requirements related to House Bill 7139 and Senate Bill 1302, also referred to as the Ocean Outfall Rule Change.
The Ocean Outfall Rule Change requires elimination of the ocean outfall disposal at the Southern Regional Wastewater Treatment Plant ("SRWWTP") by the year 2025.
On January 30, 2019, the City obtained construction permits for Deep Injection Wells No. 3 and No. 4 from the Florida Department of Environmental Protection.
The City intends to dispose of up to 39.8 MGD of secondary treated wastewater effluent from the SRWWTP and the reverse osmosis concentrate from the City's Water Treatment Plant ("WTP"), into these two Deep Injection Wells.
On June 30, 2018, the City Commission passed and adopted Resolution No. R-2018-201 which approved the issuance of an Authorization to Proceed for Work Order No. B&C 18-02 to Brown and Caldwell for professional engineering and administrative services on an as-needed basis, in an amount not to exceed $100,000.00 and Brown and Caldwell designed and provided bidding services for Deep Injection Wells No. 3 and No. 4 under this work order on an as-needed basis.
On March 14, 2019, the Department of Public Utilities staff advertised for construction services, and on April 30, 2019, two bid proposals were received and publicly opened at the SRWWTP with the fo...