File #: R-2024-084    Version: 1 Name: DCM - Art and Culture Reroof
Type: Resolution Status: Agenda Ready
File created: 2/28/2024 In control: Department of Design & Construction Management
On agenda: 3/20/2024 Final action: 3/20/2024
Title: A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Issue A Purchase Order To Provincial South, Inc., D/B/A PSI Roofing, For Roof Replacement At The Art And Culture Center In An Amount Up To $500,000.00, Based Upon The Interlocal Purchasing System Request For Proposal And Contract Number 211001 For Trades, Labor And Materials, In Accordance With Section 38.41(C)(5) Of The Procurement Code. (Piggyback)
Attachments: 1. Resolution - Art & Culture_PSI_DN.pdf, 2. PSI Roofing Tips 211001_CONTRACT_JOC.pdf, 3. Arts & Cultural Center Roofing Proposal_REV.pdf, 4. Addendum to PSI Proposal_DN.pdf, 5. TIPS JOC Expiration.pdf, 6. COI Approval_risk management.pdf, 7. COI_PSI GL 23-24.pdf, 8. COI_PSI WC 2024.pdf, 9. Piggyback Checklist Hollywood 2-26-24.pdf, 10. Piggyback Request Form 2-26-24.pdf, 11. Term Sheet - Art and Culture Center_PSI Roofing 3.6.24 - PIGGYBACK.pdf
Title
A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Issue A Purchase Order To Provincial South, Inc., D/B/A PSI Roofing, For Roof Replacement At The Art And Culture Center In An Amount Up To $500,000.00, Based Upon The Interlocal Purchasing System Request For Proposal And Contract Number 211001 For Trades, Labor And Materials, In Accordance With Section 38.41(C)(5) Of The Procurement Code. (Piggyback)

Strategic Plan Focus
Infrastructure & Facilities


Body

Staff Recommends: Approval of the attached Resolution.


Explanation:
The City has an urgent need for the replacement of the roof on the Art and Culture Center. There is evidence of extensive failure in the roofing system, as multiple stains and evidence of leaks throughout the building have occurred during rain events in the last several months. The roof leaks in several locations inside the building, causing damage to the building and the artwork within. Due to the extent of roof failure, it is not recommended to make any further roofing repairs.

In preparation for the General Obligation Bond's new addition to the Art & Culture Center, sequencing the re-roof scope before this work begins is critical and must finish prior to the start of the new addition. There are existing mechanical units in the footprint of the new building that need to be relocated to various locations on the existing roof. We've included this relocation as part of this contract so that any new flashing of the units can be done simultaneously between a mechanical contractor and the roofer. PSI and Pirtle construction are in communication and Department of Design and Construction Management ("DCM") staff are overseeing the seamless coordination of this work.

The building has active and major leaking throughout which is creating a hazardous condition as well as damaging the building and art within. A competitive procurement process was done thro...