Hollywood FL banner
File #: R-2023-140    Version: 1 Name: DCM - New Library Buildout - P2 GMP
Type: Resolution Status: Passed
File created: 4/5/2023 In control: Department of Design & Construction Management
On agenda: 5/17/2023 Final action: 5/17/2023
Title: A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute A Construction Management At Risk Phase II Construction Services Agreement with Kaufman Lynn Construction Inc. For The Broward County Second Floor Library Interior Design - Development Services Project, A Capital Improvement Project, For A Total Guaranteed Maximum Price of $ 5,848,980.93.
Attachments: 1. Resolution to Execute CMAR Phase II for 2nd floor Library (Final)-JC, 2. CMAR_Phase_II_Construction_Services_Agreement_KL_Signed_042623.pdf, 3. Exhibit A - CMAR’s Direct Construction Costs.pdf, 4. Exhibit_B_-_CMAR’s_Staff_General_Condition_Costs,_Construction_Contingency_and_Fee, 5. Exhibit C - Project Schedule and List of Contract Documents.pdf, 6. Exhibit_E_-_CMAR_Project_Team, 7. Exhibit F - CMAR’s GMP Qualifications & Clarifications.pdf, 8. Exhibit_G_-_Pre-Construction_Services_Agreement, 9. Exhibit _H_Third Amendment to Ground Lease for Hollywood Library (Final Version).pdf, 10. Form_1_-_Performance, 11. Form_2_-_Payment_Bond, 12. R-2021-170, 13. COI_-_City_of_Hollywood_Florida, 14. 2023-05-07 KL Library(00A).pdf
Title
A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute A Construction Management At Risk Phase II Construction Services Agreement with Kaufman Lynn Construction Inc. For The Broward County Second Floor Library Interior Design - Development Services Project, A Capital Improvement Project, For A Total Guaranteed Maximum Price of $ 5,848,980.93.

Strategic Plan Focus
Infrastructure & Facilities


Body

Staff Recommends: Approval of the attached Resolution.


Explanation:
On July 7, 2021, the City Commission passed and adopted Resolution No. R-2021-170 authorizing City officials to negotiate Phase I preconstruction services with the highest-ranked firm, Kaufman Lynn Construction, Inc. to provide Construction Manage at Risk services for the Second Floor Library build out and miscellaneous City Hall and site work project, a capital improvement project.

On December 6, 2021, a Phase I Pre-construction Services agreement was executed for the Broward County Second Floor Library Interior Design - Development Services project in an amount not to exceed of $54,811.00.

Kaufman Lynn Construction, Inc. Phase I services have been completed and Kaufman Lynn Construction, Inc. has provided the Design and Construction Management Department ("DCM") with a Guaranteed Maximum Price ("GMP") proposal for the construction of the Second Floor Library build out Project in an amount not to exceed $ 5,848,980.93, which staff has determined to be fair and reasonable and in accordance with industry standards.

It is in the best interest of the City to enter into an agreement with Kaufman Lynn Construction, Inc. to provide Phase II construction services for the Broward County Second Floor Library build out project pursuant to the attached agreement.

The Director of DCM recommends that the City Commission approve and authorize the execution of the attached Construction Management at Risk Phase II Co...

Click here for full text