File #: R-2023-032    Version: 1 Name: DCM- Tidal Flooding Cummins Contract Amendment
Type: Resolution Status: Passed
File created: 12/15/2022 In control: Department of Design & Construction Management
On agenda: 1/18/2023 Final action: 1/18/2023
Title: A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute An Amended And Restated Contract To The Agreement With Cummins Cederberg, Inc. For Engineering, Surveying, And General Consulting Services For Phases 2 And 3 Of The Tidal Flooding And Shoreline Protection Projects, A General Obligation Bond Project, With 50 Percent Project Funding By A Florida Department Of Environmental Protection Grant In The Amount Of $1,833,910.00.
Attachments: 1. 00-Resolution - Contract Amendment Cummis Tidal Flooding 2 3- FDEP - Procurement Approved Updated, 2. 03-PSA - Contract Amendment -Cummins Cederberg Tidal Flooding - PC, 3. 04-Exhibit A-22FRP13-TIDAL FLOODING MITIGATION & SHORELINE PROTECTION, 4. 05-Exhibit B Part 1-Cummins Cederberg PSA Tidal Flooding Phase I, 5. 06-Exhibit B Part 2-Cummins PSA Tidal flooding Phase I, 6. 07-Exhibit C (2022-10-27) PRO-A1R2 Hollywood Tidal Flooding Mitigation Phases 2 & 3, 7. COI-City of Hollywood, WOS, Hollywood, FL, 33020-4807, 8. R-2018-386 - signed, 9. R-2020-072, 10. R-2020-275, 11. R-2022-281 (1)

Title

A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute An Amended And Restated Contract To The Agreement With Cummins Cederberg, Inc. For Engineering, Surveying, And General Consulting Services For Phases 2 And 3 Of The Tidal Flooding And Shoreline Protection Projects, A General Obligation Bond Project, With 50 Percent Project Funding By A Florida Department Of Environmental Protection Grant In The Amount Of $1,833,910.00.

 

Strategic Plan Focus

Resilience & Sustainability

 

 

Body

 

Staff Recommends:   Approval of the attached Resolution.

 

Explanation:

On March 12, 2019, the City held a Special Election wherein a majority of voters approved funding, through a General Obligation Bond (“GOB”), for the Tidal Flooding Mitigation and Shoreline Protection Project. The project’s purpose was to provide tidal barriers to the City-owned properties most vulnerable to tidal flooding, around the two man-made inlets known as North Lake and South Lake. 

 

On April 22, 2020, under R-2020-072, Cummings Cederberg was selected as the consultant for the Tidal Flooding Mitigation and Shoreline Protection project, including all the City-owned parcels around North and South Lake and shown as 22 parcels in a map that was made part of the Request for Qualifications. A preliminary cost estimate showed that the GOB funds were insufficient to design and construct the needed tidal barriers for all 22 parcels.

 

The project was divided into 22 smaller projects, matching the parcel map, and classified by phases. Eight locations were classified as Phase 1 projects.

 

The design consultant agreement, approved under R-2020-275, stipulated that the award for Phase 1 projects be developed from survey, planning, permitting, final design and construction engineering services. Fourteen projects were classified as either Phase 2 or Phase 3 projects.  The scope of services included only the development of conceptual designs for Phases 2 and 3. These conceptual drawings were utilized to apply for grant funding.

 

The Department of Design and Construction Management (“DCM”), on behalf of the City, submitted a grant application to the State of Florida Department of Environmental Protection (“FDEP”) for funding through its Resilient Florida Grant Program in the amount of $14,112,000.00 to assist in funding the design, permitting and construction of Phases 2 and 3 of the Tidal Flooding and Shoreline Protection Project.

 

The FDEP awarded the City a total of $14,112,000.00 to fund the design documents and construction of the entire Tidal Flooding and Shoreline Protection Project, including Phases 1, 2 and 3. The City will be able to recover 50 percent of the project costs, for all three phases, incurred after the award date of July 1, 2021, up to the grant award total.

 

In order to meet the FDEP grant requirements, DCM negotiated a scope of work and a fee of $1,833,910.00 with Cummins Cederberg, Inc. for the design, permitting, bidding and construction phase engineering services of the remaining 14 locations identified as Phase 2 and 3 Projects.

 

The Director of DCM recommends that the City Commission authorize the appropriate City officials to execute the attached Contract Amendment to the Agreement with Cummins Cederberg, Inc. in the amount of $1,833,910.00.

 

 

Fiscal Impact:

Funding for this project was included in the amended FY 2023 Capital Improvement Plan and is available in account number 333.149901.54100.563010.001187.000.000.

 

 

Recommended for inclusion on the agenda by:

Jose Cortes, Director, Design and Construction Management

Gus Zambrano, AICP, Assistant City Manager/Sustainable Development