File #: R-2020-035    Version: 1 Name: ATP AEC 20-01 Lift Station E-14 Rehabilitation
Type: Resolution Status: Passed
File created: 1/8/2020 In control: Department of Public Utilities
On agenda: 2/5/2020 Final action: 2/5/2020
Title: A Resolution Of The City Commission Of The City Of Hollywood, Florida, Authorizing The Appropriate City Officials To Issue An Authorization To Proceed With AECOM Technical Services, Inc. For Work Order No. AEC 20-01 To Provide Professional Engineering Services For Design And Construction Services Related To Lift Station E-14's Rehabilitation And Replacement, Located At 1480 Three Island Boulevard, In An Amount Not Exceed $99,958.00.
Attachments: 1. 01 Resolution - AEC 20-01 LS E-14 Rehab.pdf, 2. 02 ATP AEC 20-01 - LS E-14 Rehab _ $99,958.00.pdf, 3. 03 R-2017-284 (Executed).pdf, 4. 04 R-2017-284 Professional Services Agreement (Executed).pdf, 5. 05 Proposal - AEC 20-01 LS E-14 Rev2 2019 10 31.pdf, 6. TermSheetATPAECOMPROFSERVLIFTSTATION.pdf, 7. BIS 20-075.pdf

Title

A Resolution Of The City Commission Of The City Of Hollywood, Florida, Authorizing The Appropriate City Officials To Issue An Authorization To Proceed With AECOM Technical Services, Inc. For Work Order No. AEC 20-01 To Provide Professional Engineering Services For Design And Construction Services Related To Lift Station E-14’s Rehabilitation And Replacement, Located At 1480 Three Island Boulevard, In An Amount Not Exceed $99,958.00.

 

Body

 

Staff Recommends: Approval of the attached Resolution.

 

 

Explanation:

Lift Station E-14 has served Harbor Islands for more than 25 years and requires extensive structural rehabilitation and equipment replacement.

 

AECOM and the City currently have a continuing Professional Services Agreement for General Engineering Consulting Services for water, sewer, reuse and stormwater infrastructure projects, and this agreement was approved by the City Commission pursuant to Resolution No. R-2017-284.

 

The Department of Public Utilities staff requested a proposal from AECOM to provide professional engineering services related to the design, permitting, bidding, and construction services for the Lift Station E-14 Rehabilitation project.

 

The agreement has a provision for insurance and indemnification that meets the City’s requirements and gives the City the right to terminate for convenience.

 

The Department of Public Utilities recommends that the City Commission authorize the appropriate City officials to issue the attached Authorization to Proceed for work order number AEC 20-01 with AECOM in an amount not to exceed $99,958.00.

 

Funding was included in the FY 2020 Capital Improvements Program that was approved pursuant to Resolution No. R-2019-284.

 

Funding is available in account number 442.409901.53600.531210.001295.000.000.

 

The consultant will complete the proposed professional engineering services in approximately 18 months.

 

 

Recommended for inclusion on the agenda by:

Clece Aurelus, Engineering Support Services Manager, Department of Public Utilities

Vivek Galav, Director, Department of Public Utilities

Gus Zambrano, Assistant City Manager/Sustainable Development