File #: R-CRA-2019-03    Version: Name: Nebraska/Nevada Garage - Completion Time Extension
Type: CRA Resolution Status: Passed
File created: 12/20/2018 In control: Regular Community Redevelopment Agency Meeting
On agenda: 2/6/2019 Final action: 2/6/2019
Title: A Resolution Of The Hollywood, Florida, Community Redevelopment Agency ("CRA"), Authorizing Appropriate CRA Officials To Issue A Contract Time Extension, Without Increase of Costs, For The Nevada Parking Garage, To Be Completed By September 25, 2019.
Attachments: 1. 1 2018Additionaltime.pdf, 2. 2 CO #001_ Time Extension_ Test Pile Delay_ 12-19-18, 3. 3 BIS Garage Ext of Time, 4. tercrakaufmanlynnprkggaragetimeextension.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

A Resolution Of The Hollywood, Florida, Community Redevelopment Agency (“CRA”), Authorizing Appropriate CRA Officials To Issue A Contract Time Extension, Without Increase of Costs, For The Nevada Parking Garage, To Be Completed By September 25, 2019. 

 

 

Body

 

Staff Recommends: Approval of the attached Resolution.

 

 

Explanation:

The Nevada Parking Garage Project includes construction of a new parking garage. On July 3, 2017, the CRA Board awarded Kaufman Lynn Construction Inc. a Construction Management contract in the amount of $13,109,688.00 to construct a new parking garage located between Nebraska and Nevada Street and A1A. Due to unforeseen soil condition issues at the new parking garage site between Nevada and Nebraska Streets, there is a need for a time extension of contract for the Nevada Parking Garage without increase of costs. The requested contract time extension will require project completion by September 25, 2019. The Executive Director of the CRA recommends approval of the time extension.

 

 

Recommended for inclusion on the agenda by:

Jorge Camejo, Executive Director