Hollywood FL banner
File #: R-CRA-2019-05    Version: 1 Name: Damaged Pole Replacement Project
Type: CRA Resolution Status: Passed
File created: 12/20/2018 In control: Regular Community Redevelopment Agency Meeting
On agenda: 1/16/2019 Final action: 1/16/2019
Title: A Resolution Of The Hollywood, Florida, Community Redevelopment Agency ("CRA"), Canceling Bid BRCA 10-013 Dated November 5, 2018 For Replacement Of Damaged Poles, And Awarding The Project To Burkhardt Construction, Inc. At A Lower Cost Based On Negotiation With The Construction Management Company.
Attachments: 1. 1 2018cancelbid1218.pdf, 2. 2 Bid Tabulation.pdf, 3. 3 Sagaris.pdf, 4. 4 AUM.pdf, 5. 5 BIS Pole Replacement, 6. tercraburkhardtreplacepoles.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

A Resolution Of The Hollywood, Florida, Community Redevelopment Agency (“CRA”), Canceling Bid BRCA 10-013 Dated November 5, 2018 For Replacement Of Damaged Poles, And Awarding The Project To Burkhardt Construction, Inc. At A Lower Cost Based On Negotiation With The Construction Management Company.

 

Body

 

Staff Recommends: Approval of the attached Resolution.

 

 

Explanation:

Staff identified 13 damaged concrete poles along the beach that were damaged by the salt environment and needed to be replaced. Staff prepared bid documents and estimated the project at a cost of $65,000.00. On November 5, 2018 the CRA bid out this project as low bid and on December 11, 2018, two bids were received and opened. The low bids were as follows: Sagaris Group, $90,000.00; and AUM Construction, $146,050.00.

Since the bids came in higher than the estimated cost and in order to lower the construction cost to an acceptable amount, staff requested a proposal from Burkhardt Construction, Inc. Pursuant to R-CRA-2016-54 the CRA Board ranked Burkhardt Construction Inc. (CM) as the firm to provide construction management services for various projects within the CRA districts. The CM provided a proposal for the pole replacement project at a lower cost of $68,231.06. Since the project cost is less than $200,000.00, the CRA Board can waive the requirement for bonds which will result in a further cost reduction in the amount of $940.63. The CRA Executive Director recommends canceling the low bid, and accepting the CM proposal without the bonds.

 