File #: R-2017-368    Version: 1 Name: Sanitary Sewer Lift Station W-14 Rehab Amend No. 1 ATP CTA 17-01 (CTA 16-8063)
Type: Resolution Status: Passed
File created: 10/25/2017 In control: Department of Public Utilities
On agenda: 12/6/2017 Final action: 12/6/2017
Title: A Resolution Of The City Commission Of The City Of Hollywood, Florida, Authorizing The Appropriate City Officials To Issue The Attached Amendment No. 1 To The Authorization To Proceed For Work Order No. CTA 17-01 Between Craven Thompson & Associates, Inc. And The City Of Hollywood To Provide Professional Engineering Services For Design And Construction Services Related To Flowmeter And By-Pass Piping Servicing Sanitary Sewer Lift Station W-14 Rehabilitation Project, In A Lump Sum Amount Of $15,200.00 (Project No. 16-8063).
Attachments: 1. 1 Resolution - Sanitary Sewer Lift Station W-14 Rehab Amend No. 1 ATP CTA 17-01 (CTA 16-8063).pdf, 2. 2 ATP CTA 17-01 Amend #1- Sanitary Sewer Lift Station W-14 Rehab Amend No. 1 ATP CTA 17-01 (CTA 16-8063).pdf, 3. 3 ATP CTA 17-01 - Sanitary Sewer Lift Station W-14 Rehab Amend No. 1 ATP CTA 17-01 (CTA 16-8063).pdf, 4. 4 Proposal - Sanitary Sewer Lift Station W-14 Rehab Amend No. 1 ATP CTA 17-01 (CTA 16-8063).pdf, 5. 5 R-2017-015 Craven Thompson Sanitary Sewer Lift Station W-14.pdf, 6. Term Sheet - Craven Thompson, Work Order 17-01.pdf, 7. BIS 18-046.pdf
Title
A Resolution Of The City Commission Of The City Of Hollywood, Florida, Authorizing The Appropriate City Officials To Issue The Attached Amendment No. 1 To The Authorization To Proceed For Work Order No. CTA 17-01 Between Craven Thompson & Associates, Inc. And The City Of Hollywood To Provide Professional Engineering Services For Design And Construction Services Related To Flowmeter And By-Pass Piping Servicing Sanitary Sewer Lift Station W-14 Rehabilitation Project, In A Lump Sum Amount Of $15,200.00 (Project No. 16-8063).


Body

Staff Recommends: Approval of the Attached Resolution


Explanation:
The Sanitary Sewer Lift Station W-14, located at 5596 Monroe Street, was installed in 1971 and most of the equipment and internal piping and valves at the station have reached their useful lives.

On January 18, 2017, via Resolution R-2017-015 the City awarded the professional technical services for the design, permitting, bidding, and construction services to Craven Thompson & Associates, Inc. in the amount of $178,785.00.

As a new design/operation standard, the Department of Public Utilities staff decided to install flowmeters at all new sewer lift stations.

The Department of Public Utilities staff also decided to install by-pass piping to provide operational flexibility for the sewer Lift Station W-14.

The flowmeter and by-pass piping were not included in the original consulting services scope of the Lift Station W-14 Rehabilitation project.

The City requested a proposal from Craven Thompson & Associates, Inc. to provide Professional Engineering Services for the design and construction services related to the installation of the new flowmeter and the by-pass piping for the Lift Stations W-14 Rehabilitation project.

The Department of Public Utilities staff recommends that the City Commission authorize the appropriate City Officials to issue the attached Amendment No. 1 to Authorization to Proceed for Work Order No. CTA 17-01 between Craven Thompson & As...