Title
A Resolution Of The City Commission Of The City Of Hollywood, Florida, Authorizing The Appropriate City Officials To Execute The Attached Authorization To Proceed For Work Order No. ANA 17-01 Between Atkins North America, Inc. And The City Of Hollywood To Provide Professional Engineering Services For The Water Main Replacement Program From Hollywood Boulevard To Sheridan Street And Between N. 31st Avenue And N. 35th Avenue Including The Design And Permitting Of A Reuse Water Main Along Johnson Street From N. Park Road To N. 56th Avenue, As Identified In The 2007 Water System Master Plan, In The Amount Of $1,172,908.00 (Project No. 16-5135).
Body
Staff Recommends: Approval of the attached Resolution
Explanation:
The 2007 Water System Master Plan identified the need to replace aging water distribution system pipes throughout the City of Hollywood.
The City of Hollywood water distribution system consists of over 600 miles of pipelines with diameters ranging from 2-inches to 36-inches.
In order to address the findings of the 2007 Water System Master Plan, the Department of Public Utilities developed and is implementing a City-wide Water Main Replacement Program.
The Water Main Replacement Program prioritizes the replacement of the water mains based on the age of the pipelines, type of pipe material, repeated pipeline breaks in the areas, and water quality issues.
The City requested a proposal from Atkins North America, Inc. to provide professional engineering services for the design, permitting, bidding, and construction services for the proposed water main.
Atkins North America, Inc. and the City of Hollywood have a Professional Services Agreement for General Engineering Consulting Services for water and sewer infrastructure projects, and this agreement was approved by the City Commission by Resolution No. R-2009-214 on July 15, 2009; renewed by the City commission via Resolution No. R-2013-110 on May 1, 2013; renewed by the City commission via Resolution No. R-2015-068 on April 1, 2015; and this agreement has a provision for insurance and indemnification that meets the City’s requirements and gives the City the right to terminate for convenience.
The Administration recommends that the City Commission authorize the appropriate City Officials to execute the attached Authorization to Proceed for Work Order No. ANA 17-01 between Atkins North America, Inc. and the City of Hollywood, together with such nonmaterial changes as may be subsequently agreed to by the City Manager and approved as to form and legality by the City Attorney, in the amount of $1,172,908.00.
Funding for Water Main Replacement Program and Reuse System Infrastructure Program was included in the in the FY 2017 Capital Improvements Program that was approved via Resolution R-2016-285.
Funding for the Water Main portion is available in account number 42.4000.76663.536.323121.
Funding for the Reuse Infrastructure portion is available in account number 42.4000.90715.536.063121.
The tasks included in the proposal will be implemented in phases and the design services will be completed in approximately twelve (12) months.
Recommended for inclusion on the agenda by:
Dr. Wazir Ishmael, City Manager
George R. Keller, Jr., ACM, Finance and Administration
Gus Zambrano, ACM, Sustainable Development
Steve Joseph, Director, Public Utilities
Paul Bassar, Director & Contract Compliance, Director