Title: A Resolution Of The City Commission Of The City Of Hollywood, Florida, Committing Funding To The Johnson Street 31st Court To US-1 Complete Streets Project, And Authorizing The City Manager To Execute The Attached Commitment Letter Setting Forth The City's Commitment to the Project Pursuant to The Funding Schedule For The Right Of Way Acquisitions Portion Of The Project With An Estimated Cost Of Six Million ($6M) Dollars Over a Three Year Period.
Attachments: 1. EN17-053Reso.pdf, 2. FDOT Commitment Letter 2.2.2017 .pdf, 3. EN17-053 Exhibit A.pdf, 4. Letter From Broward MPO - Johnson St Complete Streets Project 434672-1.pdf, 5. Letter from FDOT - Johnson St Complete Streets 434672-1-52-01.pdf, 6. BIS 17-092.pdf
Title
A Resolution Of The City Commission Of The City Of Hollywood, Florida, Committing Funding To The Johnson Street 31st Court To US-1 Complete Streets Project, And Authorizing The City Manager To Execute The Attached Commitment Letter Setting Forth The City's Commitment to the Project Pursuant to The Funding Schedule For The Right Of Way Acquisitions Portion Of The Project With An Estimated Cost Of Six Million ($6M) Dollars Over a Three Year Period.

Body

Staff Recommends: Approval of the Attached Resolution.


Explanation:
The Broward County Metropolitan Planning Organization (Broward MPO), the Florida Department of Transportation (FDOT), and the City of Hollywood are committed to improving alternative modes of transportation and support Complete Streets Corridors providing safe choices to pedestrians, cyclists, transit riders and motorists. Broward MPO has allocated funds for the reconstruction of Johnson Street from 31st Court to US1 as part of its Transportation Mobility initiative; the Broward MPO funding is for the design and construction of the project which is currently estimated at $13M.

A typical local street with two way traffic, swales for drainage and sidewalks has a 50' right of way; Johnson Street east of I-95 has segments with 40' and 45' feet wide right of ways, is an alternate to Hollywood Boulevard with its two lanes of traffic and continuous center lane cross section and is heavily used by pedestrians and bicyclists without the benefit of sidewalks or bike lanes. The Broward MPO and FDOT require the City to fund the right of way acquisitions estimated to cost six ($6M) Million dollars to develop this Complete Streets project, and to minimize acquisition costs and property impacts the existing 40' foot segment from 28th Avenue to 22nd Avenue will be developed as a 42' foot cross section with Sharrow Bike Lanes.

In FY 2016 Capital Improvement Plan (CIP) the City allocated $1,150,000.00 to this project, an additional $1,265,000.00 was allo...