Title
A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute Contracts With Southeastern Engineering Contractors, Inc., Man Con, Inc., And The Stout Group, LLC For Construction Services Related To 2023 Drainage Improvements In Amounts Not To Exceed $1,200,000.00, $1,000,000.00, And $800,000.00, Respectively; Approving And Authorizing The Appropriate City Officials To Execute An Authorization To Proceed For Work Order Number CTA 23-02 With Craven, Thompson & Associates, Inc. In An Amount Not To Exceed $500,000.00 For As Needed Support Of Design And Construction Administration For This Project.
Strategic Plan Focus
Infrastructure & Facilities
Body
Staff Recommends: Approval of the attached Resolution.
Explanation:
The Department of Public Utilities ("Department") needs qualified firms to provide construction services in various areas throughout the City to address routine flooding conditions following regular rain events.
As part of this ongoing drainage improvements program, the Department recommends that projects, including but not limited to the following list, be designed and constructed over the next two years:
* 1179 Johnson Street - Outfall Replacement
* S 12 Avenue and N Southlake Drive - 60" Flap Gate Replacement
* 1000 Washington Street - 24" Flap Gate Replacement
* Stormwater Pump Station SW-09 Wet Well Retaining Wall Repair/Replacement
* 5130 McKinley Street and Emerson Drive - Swale Restoration
* 724 Park Court - Drainage System Installation
* 2034 Thomas Street - Drainage System Installation
* 1200 Van Buren Street - Regrading
* Polk Street and N 14 Court - Swale Restoration
* 2722 Scott Street - Drainage and connection to an existing outfall
* 3621 N 52 Avenue - Drainage and connection to an existing outfall
* 3110 N 52 Avenue - Drainage and connection to an existing outfall
* Connection from Liberty Street Lake through Rotary Park to the C-10 Canal