A Resolution Of The City Commission Of The City Of Hollywood, Florida, Ranking Construction Management At Risk Firms And Authorizing The Appropriate City Officials To Negotiate Phase I Preconstruction Services With The Highest Ranked Firm, Kaufman Lynn Construction, Inc. To Provide Construction Management At Risk Services For The Second Floor Library Build-Out And Miscellaneous City Hall And Site Work Project, A Capital Improvement Project.
Strategic Plan Focus
Infrastructure & Facilities
Body
Staff Recommends: Approval of the Attached Resolution.
Explanation:
On May 14, 2002, officials from the City of Hollywood and Broward County executed an Interlocal Agreement and Ground Lease, and subsequently executed amendments to the agreements to address parking and the construction of a shell space for the second floor of the library to be utilized by the City.
The Department of Development Services has been undergoing changes to improve efficiency and customer service, and is processing a record number of building permits reflecting renewed investment in the City by residents, developers and businesses.
Synalovski Romanik Saye, LLC is providing Architectural Design Services to complete the second floor library office build-out project.
The City has followed the procedures set forth in Section 255.20 of Florida Statutes, Section 287.055, entitled "Consultants' Competitive Negotiation Act" ("CCNA") and the City's Procurement Code to advertise for Statements of Qualifications for Construction Management at Risk services. The City advertised a Request for Qualifications to provide Construction Management at Risk services on Bidsync on April 13, 2021, with the Request for Qualifications attached, and provided a scope of the project and selection criteria to be used for ranking the responses.
Statements of Qualifications were received on May 17, 2021 from the following six firms:
1. State Contracting & Engineering Corporation
2. Gilbane Building Company...