Hollywood FL banner
File #: R-2024-364    Version: 1 Name: RAS Pump Station No. 1 Change Order No. 3
Type: Resolution Status: Passed
File created: 10/8/2024 In control: Department of Public Utilities
On agenda: 11/6/2024 Final action: 11/6/2024
Title: A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute Change Order No. 3 To Extend The Contract With Intercounty Engineering, Inc. For The RAS Pump Station No. 1 Replacement Project By 363 Days Due To Unforeseen Site Condition Delays In Accordance With Section 38.48 Of The Procurement Code. (Change Orders)
Attachments: 1. Resolution RAS Pump Station No. 1 CO3.pdf, 2. Change Order No. 03 - RAS Pump Station No. 1 Replacement.pdf, 3. Delay Claim Letter - RAS Pump Station No. 1 Replacement.pdf, 4. R-2020-063 Intercounty RAS Pump Station No. 1 Replacement.pdf, 5. R-2024-040 RAS Pump Station No. 1 Replacement Change Order No. 2.pdf, 6. Contract Book (Executed) - RAS PS No. 1 Replacement (9523).pdf
Title
A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute Change Order No. 3 To Extend The Contract With Intercounty Engineering, Inc. For The RAS Pump Station No. 1 Replacement Project By 363 Days Due To Unforeseen Site Condition Delays In Accordance With Section 38.48 Of The Procurement Code. (Change Orders)

Strategic Plan Focus
Infrastructure & Facilites


Body

Staff Recommends: Approval of the attached Resolution.


Explanation:
On April 22, 2020, pursuant to Resolution No. R-2020-063, the City Commission authorized the appropriate City officials to execute a contract with Intercounty Engineering, Inc. ("Intercounty") for construction services related to the Return Activated Sludge ("RAS") Pump Station No. 1 Replacement Project at the Southern Regional Wastewater Treatment Plant ("SRWWTP") in the amount of $3,991,828.00. On February 7, 2024, the City Commission passed Resolution No. R-2024-040 authorizing the appropriate City officials to execute Change Order No. 2 with Intercounty in an amount up to $428,450.68, and to extend the RAS Pump Station No. 1 Replacement Project's contract duration by 481 days due to COVID-19 related procurement and unforeseen site condition delays per section 38.48 of the Procurement Code.

Additional construction delays occurred due to extended delivery time of the 36-inch plug valve, steel walkway and the substantial ongoing construction of other projects at the SRWWTP coupled with operational issues from aging infrastructure that have severely impacted the planned construction schedule. Intercounty submitted delay claims to the City on April 3, 2024.

Hazen and Sawyer, P.C., as the construction manager and engineer of record, and Department staff evaluated the aforementioned claim and found a non-compensable time extension of 363 calendar days to be fair and reasonable.

This agenda item seeks the City Commission's approval and auth...

Click here for full text