Title: A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute A Contract With Layne Christensen Company In The Amount Of $200,010.00 For Mechanical Integrity Testing Of Deep Injection Wells No. 1 And No. 2 In The Southern Regional Wastewater Treatment Plant; Approving And Authorizing The Appropriate City Officials To Execute An Authorization To Proceed For Work Order Number H&S 22-06 With Hazen And Sawyer, P.C. In An Amount Not To Exceed $23,729.00 For Construction Administration Services For The Project.
Attachments: 1. Resolution- SRWWTP Injection Well Nos_1 & 2 MIT.pdf, 2. ATP H&S 22-06 _ SRWWTP Injection Well Nos_1 & 2 MIT.pdf, 3. Contract - SRWWTP Injection Well Nos_ 1 & 2 MIT.pdf, 4. Contract Book - SRWWTP Injection Well Nos_ 1 & 2 MIT.pdf, 5. H&S Proposal - SRWWTP Injection Well Nos_1 & 2 MIT.pdf, 6. Layne Christenson Bid Proposal -SRWWTP Injection Well Nos_ 1 & 2 MIT.pdf, 7. AC Shultes Bid Proposal - SRWWTP Injection Well Nos_1 & 2 MIT.pdf, 8. All Webbs Enterprise Bid Proposal - SRWWTP Injection Well Nos_ 1 & 2.pdf, 9. Florida Design Drilling Bid Proposal - SRWWTP Injection Well Nos_ 1 & 2 MIT.pdf, 10. Bid Tabulation - SRWWTP Injection Well Nos_1 & 2 MIT.pdf, 11. Award Recommendation Letter - SRWWTP Injection Well Nos_1 & 2 MIT.pdf, 12. TermSheetLayneMechaniclIntegrityBid.pdf, 13. TermSheetATPHazenSawyerconstructionsvcsmechintegwells.pdf
Title
A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute A Contract With Layne Christensen Company In The Amount Of $200,010.00 For Mechanical Integrity Testing Of Deep Injection Wells No. 1 And No. 2 In The Southern Regional Wastewater Treatment Plant; Approving And Authorizing The Appropriate City Officials To Execute An Authorization To Proceed For Work Order Number H&S 22-06 With Hazen And Sawyer, P.C. In An Amount Not To Exceed $23,729.00 For Construction Administration Services For The Project.


Strategic Plan Focus
Infrastructure & Facilities


Body

Staff Recommends: Approval of the attached Resolution.


Explanation:
The Southern Regional Wastewater Treatment Plant ("SRWWTP") is a 55.5 million gallon per day wastewater treatment facility that uses multiple treatment processes to treat wastewater and produces high quality effluent that is currently discharged into the two existing Deep Injection Wells No. 1 and No. 2 or the Atlantic Ocean. These two wells were placed in service in 2002 and are currently serving as the primary disposal method at the SRWWTP under Florida Department of Environmental Protection ("FDEP") Permit Number 156419-009-007-UO/1M. This permit requires that the five-year mechanical integrity testing program be completed before August 21, 2022, for Deep Injection Well No. 1 and before August 31, 2022 for Deep Injection Well No. 2.

On November 17, 2021, pursuant to Resolution No. R-2021-301, the City Commission authorized the appropriate City officials to execute an Authorization to Proceed for Work Order Number H&S 22-02 with Hazen and Sawyer, P.C. ("H&S") for the Design of Mechanical Integrity Testing and Operating Permit Renewal for Deep Injection Wells No. 1 and No. 2, and Facility Permit Renewal for SRWWTP in an amount not to exceed $95,148.00.

H&S completed the design of Injection Wells No. 1 and No. 2 Mechanical Integrity Testing. On...