File #: R-2023-403    Version: 1 Name: DCM: Stan Goldman Path CMAR
Type: Resolution Status: Passed
File created: 11/7/2023 In control: Department of Design & Construction Management
On agenda: 12/6/2023 Final action: 12/6/2023
Title: A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute A Construction Management At Risk Phase II Construction Services Agreement With Lebolo Construction Management, Inc. For The Stanley Goldman Memorial Park Pathway Project, For A Total Guaranteed Maximum Price Of $2,135,694.00.
Attachments: 1. Resolution to Execute CMAR Phase II Lebolo[kp], 2. CMAR Phase II Construction Services- SG Lebolo, 3. Lebolo Pre-Construction Services Agreement, 4. Lebolo GMP Stan Goldman Park, 5. COI Lebolo Construction, 6. COI Risk Management approval, 7. R-2022-271 CMAR CSA, 8. Term Sheet - CMAR LEBOLO Construction Mgmt, Inc. re Stanley Goldman Memorial Park Pathway Project - GENERAL.pdf, 9. TMP-2023-848 Stand Goldman Pathways.pdf
Title
A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute A Construction Management At Risk Phase II Construction Services Agreement With Lebolo Construction Management, Inc. For The Stanley Goldman Memorial Park Pathway Project, For A Total Guaranteed Maximum Price Of $2,135,694.00.

Strategic Plan Focus
Infrastructure & Facilities


Body

Staff Recommends: Approval of the attached Resolution.


Explanation:
The Department of Parks, Recreation, and Cultural Arts procured Craven Thompson and Associates to provide engineered drawings for the Stanley Goldman Memorial Park pathway Capital Improvement Project.

In some areas, the pathway is crumbling, slowly sliding into the C-10 canal, flooding, is too narrow in areas, or is being taken over by invasive vegetation. The pathway is to be widened, shifted away from the canal in various areas, certain invasive vegetation needs to be removed, and lighting to be added to a portion of the pathway.

On November 16, 2022, Broward County provided permit approval for the project. On May 31, 2023, the construction drawings were submitted to the Building Department for permitting.

On September 21, 2022, the City Commission passed and adopted Resolution No. R-2022-271 authorizing City officials to execute Continuing Service Agreements with the highest-ranked firms in each tier level to provide Construction Management at Risk services, with Lebolo Construction Management, Inc. being one of the firms.

On May 1, 2023, a Phase I Pre-Construction Services Agreement was executed with Lebolo Construction Management, Inc. for the Stanley Goldman Memorial Park Pathway project in an amount up to $27,000.00.

Lebolo Construction Management, Inc.'s Phase I services have been completed and they provided the Department of Design and Construction Management Department ("DCM") with a Guaranteed Maximum Price ("GMP") proposal for the renovation of t...

Click here for full text