File #: R-2025-035    Version: 1 Name: 2023 SRWWTP Maintenance Repairs Change Order No. 2
Type: Resolution Status: Agenda Ready
File created: 1/9/2025 In control: Department of Public Utilities
On agenda: 2/5/2025 Final action:
Title: A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute Change Order No. 2 With Cardinal Contractors, Inc. To Extend The 2023 Southern Regional Wastewater Treatment Plant ("SRWWTP") Maintenance Work Project By 365 Days And Approve And Authorize The City Manager Or His Designee, To Utilize Available Contingency And The Remaining Contract Funds As Set Forth In The Contract To Complete Other Urgent SRWWTP Repairs Including The Replacements Of Grit Chamber No. 1 And No. 2 Mechanisms.
Attachments: 1. Resolution WWTP Maintenance Work CO 2.pdf, 2. Change Order No. 2 - WWTP Maintenance Work (9626).pdf, 3. Change Order No. 1 (Executed) - 2023 SRWWTP Maintenance Work (23-9626).pdf, 4. R-2023-280 Cardinal Contractors and B&C 23-03 WWTP Maintenance Project.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute Change Order No. 2 With Cardinal Contractors, Inc. To Extend The 2023 Southern Regional Wastewater Treatment Plant ("SRWWTP") Maintenance Work Project By 365 Days And Approve And Authorize The City Manager Or His Designee, To Utilize Available Contingency And The Remaining Contract Funds As Set Forth In The Contract To Complete Other Urgent SRWWTP Repairs Including The Replacements Of Grit Chamber No. 1 And No. 2 Mechanisms.

Strategic Plan Focus
Infrastructure & Facilites


Body

Staff Recommends: Approval of the attached Resolution.


Explanation:
On September 6, 2023, pursuant to Resolution No. R-2023-280, the City Commission authorized the appropriate City officials to execute a contract with Cardinal Contractors, Inc. ("Cardinal") for construction services related to the 2023 SRWWTP Maintenance Work Project, which includes five urgent work packages in an amount up to $10,849,710.00 and required fast-tracked completion within 365 days.

During construction, oxygenation train No. 4 could not be shut down as required due to unanticipated operational constraints from related process failures. The project was further delayed by the contract requirement to test the operation of one of the new polymer dosing units before replacing eight additional units. The mechanisms in Grit Chamber No. 1 and No. 2 had failed and City requested a proposal from the manufacturer through Cardinal in September 2024.

On December 5, 2024, the City Manager approved Change Order No. 1 to extend the contract completion date to March 6, 2025. The Department of Public Utilities ("Department") decided to extend the contract for an additional 365 days to replace the failed grit chamber mechanisms, due to the anticipated significant manufacturing time.

The Department Director and the Chief Procurement Officer recommend that the City Commissi...