Title
A Resolution Of The City Of The City Commission Of The City Of Hollywood, Florida, Authorizing The Appropriate City Officials To Execute The Attached Change Order No. 2 To The Contract Between Exceletech Coating & Applications, LLC And The City Of Hollywood For A Time Extension Of Two Hundred Fifty-Five (255) Calendar Days And No Cost Increase For Unforeseen Site Conditions Related To The Bar Screen Chamber Rehabilitation At The Southern Regional Wastewater Treatment Plant (Project No. 12-9214A).
Body
Staff Recommends: Approval of the attached resolution
Explanation:
The 2008/2009 Wastewater System Master Plan Identified The Need To Rehabilitate The Existing Bar Screen Chamber At The Southern Regional Wastewater Treatment Plant.
On June 20, 2012, Via Resolution No. R-2012-188, The City Commission Approved The Execution Of An Agreement Between The City Of Hollywood And Exceletech Coating & Applications, LLC For Construction Services Related To Concrete Repair/Coating Of the Bar Screen Chamber Walls And Ceiling Slabs Under The Bar Screen Chamber Rehabilitation Project At The Southern Regional Wastewater Treatment Plant.
City of Hollywood Staff, As Agreed By The Contractor, Has Executed One (1) Change Order To Date.
Pursuant To Section 38.47(A) Of The Purchasing Ordinance Of The City Of Hollywood, Change Order Means Changes, Due To Unanticipated Conditions Or Developments, Made To An Executed Contract, Which Are Reasonably And Conscientiously Viewed As Being In Fulfillment Of the Original Scope Of The Contract And/Or Matters Directly Related Thereto.
Pursuant To Section 38.47(B)(2)(A) And (B), The City Manager Is Not Authorized To Approve A Change Order Where The Cumulative Effect Of All Approved Change Orders Will Result In The Extension Of A Contract Completion Date By More Than 180 Calendar Days.
Change Order No. 1 Deducted $13,546.64 From The Cost Of The Deleted Work And Granted An 89-Day Time Extension.
During The Concrete Surface Pr...
Click here for full text