Hollywood FL banner
File #: R-2025-116    Version: 1 Name: DCM - Tidal Flooding CEI Services Corradino
Type: Resolution Status: Agenda Ready
File created: 3/26/2025 In control: Department of Design & Construction Management
On agenda: 4/16/2025 Final action:
Title: A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute An Authorization To Proceed With The Corradino Group, Inc. To Provide Construction Engineering Inspection Services During The Construction Of The Hollywood Tidal Flooding Mitigation And Shoreline Protection Sites 3, 4, 5, 11, 12, 7, 8, 14, 15 And 16 (FDEP 22FRP13), A General Obligation Bond Project, In An Amount Up To $236,384.00.
Attachments: 1. Reso Rev Award CEI Corradino for IFB -267-25-WV Tidal flooding Sites -kpwvkzp.pdf, 2. A-014- Corradino CEI CSA Tidal Flooding ATP - Mayor REV.pdf, 3. COI The Corradino Group Inc - City of Hollywood - 25032132876784 - 570111556723.pdf, 4. R-2021-208.pdf, 5. R-2022-281 (1).pdf, 6. R-2023-402.pdf, 7. R-2025-072.pdf, 8. The_Corradino_Group,_Inc._Professional_CSA_-_Construction_Engineering_Inspections.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute An Authorization To Proceed With The Corradino Group, Inc. To Provide Construction Engineering Inspection Services During The Construction Of The Hollywood Tidal Flooding Mitigation And Shoreline Protection Sites 3, 4, 5, 11, 12, 7, 8, 14, 15 And 16 (FDEP 22FRP13), A General Obligation Bond Project, In An Amount Up To $236,384.00.

Strategic Plan Focus
Resilience & Sustainability


Body


Staff Recommends: Approval of the attached Resolution.


Explanation:
On March 12, 2019, the City held a Special Election wherein a majority of voters approved funding in the amount of $14,091,065.00, through a General Obligation Bond ("GO Bond"), for the Tidal Flooding Mitigation and Shoreline Protection Project ("Project"). The Project's purpose was to provide tidal barriers to the City-owned properties most vulnerable to tidal flooding, around the two man-made inlets known as North Lake and South Lake.

On September 21, 2022, the City Commission passed and adopted Resolution No. R-2022-281, authorizing the appropriate City officials to accept and execute FDEP Resilient Florida Grant ("Agreement No. 22FRP13"), and authorizing the required match amount to be paid from GO Bond funds.

FDEP requested updates to Agreement No. 22FRP13's exhibits and attachments ("Amendment 1"), and the revised Grant Work Plan providing for the City to fund all design and construction administration costs which will count as grant match, with the City to fund construction costs not less than $12,204,935.00 and FDEP to fund construction costs up to $14,112,000.00.

FDEP also requested the Project be titled "Hollywood Tidal Flooding Mitigation and Shoreline Protection" going forward. This Amendment 1 was approved by the City Commission on December 6, 2023; also approving and authorizing the appropriate City Officials to execute all applicable grant doc...

Click here for full text