Skip to main content
Hollywood FL banner
File #: R-2024-378    Version: 1 Name: ATP ARC 25-03 SRWWTP Switchgear Replacement
Type: Resolution Status: Passed
File created: 10/22/2024 In control: Department of Public Utilities
On agenda: 11/20/2024 Final action: 11/20/2024
Title: A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute An Authorization To Proceed For Work Order Number ARC 25-03 With Arcadis U.S., Inc. For Professional Engineering Services For The Switchgear Replacement Project At The Southern Regional Wastewater Plant In An Amount Up To $537,183.00.
Attachments: 1. Resolution - ARC 25-03 SRWWTP Switchgear Replacement.pdf, 2. ATP ARC 25-03 - SRWWTP Switchgear Replacement.pdf, 3. Proposal - ARC 25-03 SRWWTP Switchgear Replacement.pdf, 4. Consulting Agreement 1324A - Arcadis US, Inc.pdf, 5. R-2023-251 (Executed).pdf
Title
A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute An Authorization To Proceed For Work Order Number ARC 25-03 With Arcadis U.S., Inc. For Professional Engineering Services For The Switchgear Replacement Project At The Southern Regional Wastewater Plant In An Amount Up To $537,183.00.

Strategic Plan Focus
Infrastructure & Facilites


Body

Staff Recommends: Approval of the attached Resolution.


Explanation:
The Department of Public Utilities ("Department") operates and maintains the 55.5 million gallon per day Southern Regional Wastewater Treatment Plant ("SRWWTP"), which includes various sewage treatment processes essential for protecting public health and safety.

The Department needs to replace critical electrical switchgear substations and motor control centers at the SRWWTP, which equipment is original, up to 40 years old, and increasingly challenging to repair since the original manufacturers are no longer in business.

On August 30, 2023, the City Commission passed and adopted Resolution No. R-2023-251, which authorized the execution of continuing professional consulting engineering services agreements with five firms for Water Treatment Plant and SRWWTP Projects, one of the firms being Arcadis U.S., Inc. ("Arcadis").

Department staff requested a proposal from Arcadis for the necessary professional engineering services for the SRWWTP Switchgear Replacement Project ("Switchgear Project"), including a technical memorandum, construction plans, and other documents, as well as permitting and bidding support. Arcadis submitted a proposal to provide said engineering services in an amount up to $537,183.00, based on the hourly rate schedule established in the Professional Services Agreement with Arcadis dated October 31, 2023. Department staff reviewed the proposal submitted by Arcadis and determined that the scope and fees are fair, reasonable, and in accordance...