File #: R-CRA-2024-60    Version: 1 Name: Correction to Ph-4 GMP Amount
Type: CRA Resolution Status: Agenda Ready
File created: 11/5/2024 In control: Regular Community Redevelopment Agency Meeting
On agenda: 12/4/2024 Final action:
Title: A Resolution Of The Hollywood, Florida Community Redevelopment Agency ("CRA"), Relating To Phase II Construction Services For The Phase IV - Undergrounding Of Overhead Utilities And Streetscape Beautification At State Road A1A From Hollywood Boulevard To The Southern City Limits, And The Florida Department Of Transportation Resurfacing Restoration And Rehabilitation At State Road A1A From Monroe Street To Seacrest Parkway; Correcting Certain Dollar Amounts Contained In Resolution No. R-CRA-2024-30.
Attachments: 1. 01 - Reso-Correction to GMP Amount Phase IV.pdf, 2. 02 - R-CRA-2024-30 - Phase IV Hollywood Boulevard Undergrounding of Ovearhead Utiities.pdf, 3. 03 - R-CRA-2024-23 - Phase IV Construction of Keating Park Project.pdf, 4. 04 - R-CRA-2023-61 - Phase II Construction Services Burkhardt Construction Inc..pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

A Resolution Of The Hollywood, Florida Community Redevelopment Agency ("CRA"), Relating To Phase II Construction Services For  The Phase IV - Undergrounding Of Overhead Utilities And Streetscape Beautification At State Road A1A From Hollywood Boulevard To The Southern City Limits, And The Florida Department Of Transportation Resurfacing Restoration And Rehabilitation At State Road A1A From Monroe Street To Seacrest Parkway; Correcting Certain Dollar Amounts Contained In Resolution No. R-CRA-2024-30.

 

Strategic Plan Focus

Infrastructure & Facilities

 

 

Body

 

Staff Recommends: Approval of the attached Resolution.

 

 

Explanation:

On July 3, 2024, the CRA Board passed and adopted Resolution No. R-CRA-2024-30, subsequently discovering certain incorrect amounts in the Resolution. The mistake stemmed from entering the amount of $1,373,553.00 instead of the correct amount of $1,303,168.34.

 

By entering the correct amount of $1,303,168.34 on to the original first GMP of $48,277,581.36, (i) the initial amount of $49,651,133.36 shall be corrected to $49,580,749.70; (ii) adding the Phase II Construction Services GMP amount of $26,525,180.55 increases the amendment amount to a total Guaranteed Maximum Price of $76,105,930.25 instead of $76,176,313.91.

 

 

Fiscal Impact:

There is a positive fiscal impact given that the correct amount of $1,303,168.34 is less than the amount shown on the approved resolution.

 

 

Recommended for inclusion on the agenda by:

Jorge Camejo, Executive CRA Director