Title
A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute An Authorization To Proceed For Work Order Number B&C 25-03 With Brown And Caldwell, To Provide Professional Engineering Services Related To The Design And Bidding Of Mechanical Integrity Testing For Deep Injection Wells No. 1, 2, 3, And 4, In An Amount Not To Exceed $65,122.00.
Strategic Plan Focus
Infrastructure & Facilites
Body
Staff Recommends: Approval of the attached Resolution.
Explanation:
Per Rule 62-528 of the Florida Administrative Code, Deep Injection Wells ("DIW") must demonstrate both internal and external mechanical integrity every 5 years. There are four DIW's in service at the Southern Regional Wastewater Treatment Plant ("SRWWTP"). The deadlines to complete mechanical integrity testing ("MIT") for these DIWs are as follows:
Injection Well No. 1 - August 20, 2027
Injection Well No. 2 - August 30, 2027
Injection Well No. 3 - April 25, 2026
Injection Well No. 4 - September 6, 2026
On August 30, 2023, the City Commission passed and adopted Resolution No. R-2023-251 authorizing the execution of five-year continuing consulting engineering services contracts with five firms for Water Treatment Plant and Southern Regional Wastewater Treatment Plant projects, one of the firms being Brown and Caldwell ("B&C"). Department staff requested a proposal from B&C to provide design and bidding services for MIT of the four deep injection wells. B&C submitted a proposal to provide these services in an amount up to $65,122.00. Department staff evaluated the scope and fee proposal, and have determined that the negotiated fee is fair, reasonable, and in accordance with industry standards.
This agenda item seeks the City Commission's approval and authorization to execute the attached Authorization to Proceed for Work Order Number B&C 25-03 with B&C to provide professional engineering se...