A Resolution Of The City Commission Of The City Of Hollywood, Florida, Authorizing The Appropriate City Officials To Execute An Authorization To Proceed With Saltz Michelson Architects, Inc. For A Retroactive Payment Related To Additional Professional Architectural And Engineering Services For Construction Administration Of The New Fire Station No. 45 In The Amount Of $25,731.51, For A Total Contract Of $403,048.77
Strategic Plan Focus
Infrastructure & Facilities
Body
Staff Recommends: Approval of the Attached Resolution.
Explanation:
On August 26, 2015, through Resolution R-2015-255, the City Commission authorized design fees for Saltz Michelson Architects, Inc. in the amount of $246,784.00.
The revised construction contract completion date for the project was April 9, 2018, however the contractor, West Construction, Inc., substantially completed the project in August 14, 2019 and is currently in litigation with the City over the enforcement of Liquidated Damages provisions.
As the construction continued past the original contract period, additional services fees were requested by the Architect and negotiated for services during the extended construction time. As allowed by City Code staff approved ATP No. 6 and ATP No. 7; the City Commission approved ATP No.8; staff approved ATP No. 9 and ATP No. 10, the City Commission approved ATP No. 11, and staff approved ATP No. 12.
ATP No. 6
22 December 2016
$11,397.50
Staff Approved
ATP No. 7
10 April 2018
$39,742.50
ATP No. 8- R-2018-285
19 June 2018
$10,501.00
Commission Approved
APT No. 9
30 September 2018
$25,569.35
Staff Approved
ATP No. 10
31 October 2018
$8,635.00
ATP No. 11-R-2019-246
20 March 2019
$21,298.83
Commission Approved
ATP No. 12
2 April 2019
$13,389.08
Staff Approved
ATP No. 13 for additional services in the amount of $25,731.51 will bring the total contract increase to $156,264.77. As per Section 38.48(B) (2) (a) of the City of Hollywood Code of Ordinances, approval of this ATP...