File #: R-2023-404    Version: 1 Name: DCM - GMP Whiting Turner NBUndergrounding
Type: Resolution Status: Passed
File created: 11/13/2023 In control: Department of Design & Construction Management
On agenda: 12/6/2023 Final action: 12/6/2023
Title: A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute A Construction Management At Risk Phase II Construction Services Agreement With The Whiting-Turner Contracting Company For The North Beach Utilities Underground Conversion, A General Obligation Bond Project, And The Hollywood Beach Utilities Improvements - Phase 1A Project, A Public Utilities Project, For A Total Guaranteed Maximum Price Of $17,466,699.33; Amending The Fiscal Year 2024 Operating Budget And Capital Improvement Plan.
Attachments: 1. Resolution - WT- CMAR Phase II NB Undergrounding, 2. Exhibit 1, 3. GMP CMAR Whiting Turner, 4. R-2021-050 - KHA - ATP 1, 5. R-2021-060 Tetra-Tech Phase 1, 6. R-2021-306 - CMAR ranking Phase I Services, 7. R-2023-260 Executed - Additional CIP Funds, 8. R-2023-300 - FY 2024 - Operating Budget, 9. R-2023-301 - FY 2024 - CIP, 10. COI - Whiting Turner, 11. Term Sheet - Whiting-Turner Contracting Co. North Beach Utilities Underground Conversion - GENERAL.pdf, 12. TMP-2023-804, 809, 880 NB Undergrounding.pdf
Title
A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute A Construction Management At Risk Phase II Construction Services Agreement With The Whiting-Turner Contracting Company For The North Beach Utilities Underground Conversion, A General Obligation Bond Project, And The Hollywood Beach Utilities Improvements - Phase 1A Project, A Public Utilities Project, For A Total Guaranteed Maximum Price Of $17,466,699.33; Amending The Fiscal Year 2024 Operating Budget And Capital Improvement Plan.

Strategic Plan Focus
Infrastructure & Facilities


Body

Staff Recommends: Approval of the attached Resolution.


Explanation:
In a special election held on March 12, 2019, voters of the City approved a variety of projects to be funded by a General Obligation Bond ("GOB"); one of these projects being the North Beach Utilities Underground Conversion project.

Under the Hollywood Beach Utility Improvements - Phase 1A project, in the 2007 Water Main System Master Plan, the City identified the need to replace old water distribution infrastructure and increase the size of the existing sanitary sewer force main in the North Beach area.

The Department of Design and Construction Management ("DCM") and the Department of Public Utilities have agreed to manage and construct these projects under one Construction Management at Risk ("CMAR") contract to reduce the cost and to minimize construction impacts to the residents.

On December 1, 2021, the City Commission passed and adopted Resolution No. R-2021-306, ranking CMAR firms and authorizing the appropriate City officials to execute Phase 1 Pre-Construction services agreement with the highest ranked firm to provide CMAR services for the combined project.

On April 19, 2022, a CMAR Phase I Pre-Construction Services Agreement was executed with The Whiting-Turner Contracting Company for the North Beach Utilities Underground Conversion project, and T...