Skip to main content
Hollywood FL banner
File #: R-2014-144    Version: 1 Name: Septic to Sewer Dixie Hwy to N 22Ave
Type: Resolution Status: Passed
File created: 5/13/2014 In control: Department of Public Utilities
On agenda: 6/4/2014 Final action: 6/4/2014
Title: A Resolution Of The City Commission Of The City Of Hollywood, Florida, Authorizing The Appropriate City Officials To Execute The Attached Contract Between Lanzo Construction Co., Florida And The City Of Hollywood For Construction Services Related To The Dixie Corridor Septic To Sewer Conversion In The Alley Between Dixie Highway And North 22nd Avenue And Between McKinley Street And Sheridan Street, A Project Identified In The 2007/2008 Wastewater System Master Plan, In The Amount Of $2,267,705.00; And To Approve An Amendment To The Approved Fiscal Year 2013 Capital Improvement Program, As Set Forth In The Attached Exhibit A (City Project No. 09-7047B).
Attachments: 1. Resolution Septic to Sewer-Dixie Hwy & N 22Ave .pdf, 2. Exhibit A Septic to Sewer-Dixie Hwy & N 22Ave.pdf, 3. Contract - Lanzo.pdf, 4. Bid Analyses-Septic to Sewer-Dixie Hwy & N 22Ave .pdf, 5. Lanzo Bid-Septic to Sewer-Dixie Hwy & N 22Ave.pdf, 6. Mancon Bid-Septic to Sewer-Dixie Hwy & N 22Ave.pdf, 7. Metro Bid-Septic to Sewer-Dixie Hwy & N 22Ave.pdf, 8. Giannetti Bid-Septic to Sewer-Dixie Hwy & N 22Ave.pdf, 9. Central Florida Bid-Septic to Sewer-Dixie Hwy & N 22Ave.pdf, 10. Term Sheet - Lanzo Constrcution Co., Florida.pdf, 11. BIS 14-160.pdf
Title
A Resolution Of The City Commission Of The City Of Hollywood, Florida, Authorizing The Appropriate City Officials To Execute The Attached Contract Between Lanzo Construction Co., Florida And The City Of Hollywood For Construction Services Related To The Dixie Corridor Septic To Sewer Conversion In The Alley Between Dixie Highway And North 22nd Avenue And Between McKinley Street And Sheridan Street, A Project Identified In The 2007/2008 Wastewater System Master Plan, In The Amount Of $2,267,705.00; And To Approve An Amendment To The Approved Fiscal Year 2013 Capital Improvement Program, As Set Forth In The Attached Exhibit A (City Project No. 09-7047B).


Body

Staff Recommends: Approval of the Attached Resolution.

Explanation:

The 2008/2009 Wastewater System Master Plan identified the need to install a functional sanitary gravity sewer system along Dixie Corridor and N. 21st Avenue and between Sheridan Street and Pembroke Road to effectively serve and to promote economic enhancement within the existing industrial and commercial corridor.

On May 1, 2013, via Resolution No. R-2013-114 the City Commission approved the construction of a portion of the Dixie Corridor Septic to Sewer Conversion along Dixie Highway between Pembroke Road and Adams Street, between Polk Street and McKinley Street and along N. 21st Avenue between Taft Street and Sheridan Street.

On September 5, 2012, via Resolution No. R-2012-263 the City Commission approved the purchase of a portion of the property located at 2114 Harding Street to house Lift Station W-08 servicing the area along Dixie Highway between McKinley Street and Sheridan Street.

The installation of this portion of the Dixie Corridor Septic to Sewer Conversion project will take place in the alley between Dixie Highway and N. 22nd Avenue between McKinley Street and Sheridan Street. The replacement of the existing water main in the alley is necessary for the installation of the new sanitary gravity se...