Title
A Resolution Of The City Commission Of The City Of Hollywood, Florida, Authorizing The Appropriate City Officials To Execute The Attached Contract Between Giannetti Contracting Corporation And The City Of Hollywood For Construction Services Related To The Water Main Replacement Program From Sheridan Street To Pershing Street And From North 22nd Avenue To North 24th Avenue, As Identified In The 2007 Water System Master Plan And As Part Of The City-Wide Water Main Replacement Program, In The Amount Of $2,868,708.00 (City Project No. 13-5121).
Body
Staff Recommends: Approval of the attached Resolution.
Explanation:
The 2007 Water System Master Plan identified the need to replace aging infrastructure throughout the City of Hollywood and to install additional infrastructure to improve the level of service within the City's water system.
The City-wide Water Main Replacement Program identified the need to replace old water distribution infrastructure and install 8-inch diameter and 4-inch diameter water mains within the area surrounded by Sheridan Street and Pershing Street and North 22nd Avenue and North 24th Avenue.
On September 18, 2013, via Resolution R-2013-266, the City Commission approved a proposal from Brown and Caldwell, Inc., in the amount of $289,992.00, to provide engineering design services, permitting services, bidding recommendation services, and limited engineering services during construction for the Water Main Replacement Program within the area surrounded by Sheridan Street and Pershing Street and North 22nd Avenue and North 24th Avenue.
On February 17, 2015, the Department of Public Utilities staff advertised the project soliciting for qualified construction services, and on March 20, 2015, nine (9) bid proposals were received at the Office of the City Clerk and were publicly opened at the City of Hollywood Southern Regional Wastewater Plant with the following results:
No.
BIDDER
BID|1313|Giannetti Contracting C...