Hollywood FL banner
File #: R-2024-242    Version: 1 Name: ATP CEI 24-01 WTP Maintenance Package B
Type: Resolution Status: Passed
File created: 6/6/2024 In control: Department of Public Utilities
On agenda: 7/3/2024 Final action: 7/3/2024
Title: A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute An Authorization To Proceed For Work Order Number CEI 24-01 With Carollo Engineers, Inc. For Professional Engineering Services Related To The Water Treatment Plant Maintenance Package B Projects In An Amount Up To $264,441.00.
Attachments: 1. Resolution - WTP Maintenance Package B.pdf, 2. ATP CEI 24-01- WTP Maintenance Package B.pdf, 3. Proposal - ATP CEI 24-01 WTP Maintenance Package B_SOW Final.pdf, 4. R-2023-251 - WTP Maintenance Package B.pdf
Title
A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute An Authorization To Proceed For Work Order Number CEI 24-01 With Carollo Engineers, Inc. For Professional Engineering Services Related To The Water Treatment Plant Maintenance Package B Projects In An Amount Up To $264,441.00.

Strategic Plan Focus
Infrastructure & Facilities


Body

Staff Recommends: Approval of the attached Resolution.


Explanation:
The Department of Public Utilities (Department) maintains and operates the City's 59.5 million gallons per day (MGD) Water Treatment Plant (WTP). The Department identified several assets at the WTP in need of maintenance, repair, or replacement, some of which are original and thus more than 50 years old. The projects identified by the Department as WTP Maintenance Package B include the following:

* Slakers 2 and 3 - Installation and Replacement of Lime Feed Pumps in Silo Nos. 2 and 3
* Filters 7 Through 18 - Surface Wash Feed Line Replacement
* Fluoride System Replacement
* Sodium Hexametaphosphate (SHMP) Feed System Replacement
* Membrane Softening/Reverse Osmosis Chemical Floor Recoating
* Mud Pump Discharge and Suction Line Reconfiguration

On August 30, 2023, the City Commission passed and adopted Resolution No. R-2023-251, which authorized the execution of continuing professional consulting engineering services contracts with five firms for water and wastewater treatment plant projects, one of the firms being Carollo Engineers, Inc. (Carollo).

The Department requested a proposal from Carollo to provide design, permitting, and bidding assistance related to the WTP Maintenance Package B projects. Carollo submitted a proposal to provide the aforementioned services in an amount up to $264,441.00.

This agenda item seeks the City Commission's approval and authorization to execute the attached Authorization to Proceed for Work Order No. CEI 24-01 with Carollo Eng...

Click here for full text