File #: R-CRA-2023-46    Version: 1 Name: ILA - Pump Station Reimbursement
Type: CRA Resolution Status: Passed
File created: 9/13/2023 In control: Regular Community Redevelopment Agency Meeting
On agenda: 10/4/2023 Final action: 10/4/2023
Title: A Resolution Of The Hollywood, Florida Community Redevelopment Agency ("CRA"), Approving And Authorizing The Appropriate CRA Officials To Execute An Interlocal Agreement With The City Of Hollywood For Reimbursement Of Costs For Funding The Design, Bidding Services Relating To Stormwater Pump Station Serving State Road A1A Between Iris Terrace And Daffodil Terrace In An Amount Up To $421,195.78.
Attachments: 1. 1. Reso - Resolution ILA.pdf, 2. 2. ILA - PUMP STATIONSPhase IV.pdf, 3. 3. Exhibit A-BCC Proposal - City of Hollywood PS Analysis and Design_R1.pdf, 4. 4. R-CRA-2022-06A - Stormwater pump Station.pdf, 5. 5. R-CRA-2021-36 - FDOT - Funding Participation for Pump Stations.pdf, 6. 6. R-2021-208 Various Eng Services Citywide.pdf, 7. Term Sheet - CRA- ILA Stormwater Pump Station.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Title
A Resolution Of The Hollywood, Florida Community Redevelopment Agency ("CRA"), Approving And Authorizing The Appropriate CRA Officials To Execute An Interlocal Agreement With The City Of Hollywood For Reimbursement Of Costs For Funding The Design, Bidding Services Relating To Stormwater Pump Station Serving State Road A1A Between Iris Terrace And Daffodil Terrace In An Amount Up To $421,195.78.

Strategic Plan Focus
Infrastructure & Facilities


Body

Staff Recommends: Approval of the attached Resolution.


Explanation:
State Road A1A ("A1A") is situated on a barrier island that separates the Atlantic Ocean from the Intracoastal Waterway and is designated as a hurricane evacuation route. Pursuant to Resolution No. R-2022-061, City entered Local Funding Agreements with Florida Department of Transportation ("FDOT") for the funding of the design of four stormwater pump stations located at Franklin Street, Sheridan Street, Van Buren Street and Bouganvilla Terrace, engaged by FDOT to address higher tide elevation and daylight flooding which is a common occurrence and poses risk to vehicles and pedestrians.

The Hollywood Community Redevelopment Agency ("CRA") and Department of Public Utilities ("Department") determined that additional stormwater pump stations need to be installed to address severe flooding between Iris Terrace and Daffodil Terrace based on recent Stormwater Master Plan findings.

On July 7, 2021, the CRA Board passed and adopted Resolution No. R-CRA-2021-36, approving and authorizing fund participation to FDOT in the amount of $3.14 million for the design and construction of three pumps stations, two of which are located withing the Phase IV project boundaries. However, the FDOT pump station design identified in resolution R-CRA-2021-36, benefits a limited area of the Phase IV project boundaries, and the need to address flooding along the remaining southernmost east/west streets is an integral part of the Phase IV resiliency efforts.

The CR...