Hollywood FL banner
File #: R-2024-329    Version: 1 Name: Jacobs ATP JEG 24-02 Asset Mgmt Consulting Services
Type: Resolution Status: Passed
File created: 8/17/2024 In control: Department of Public Utilities
On agenda: 10/1/2024 Final action: 10/1/2024
Title: A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute An Authorization To Proceed For Work Order Number Jeg 24-02 With Jacobs Engineering, Inc. For Asset Management Consulting Services In An Amount Up To $901,000.00.
Attachments: 1. 01 Resolution - JEG 24-02 Asset Management (LEGAL).pdf, 2. Consulting Agreement - Jacobs Engineering.pdf, 3. ATP - JEG 24-02 - Asset Management .pdf, 4. 20240812_TO 2 Lift Stations Condition Assessment_Executed.pdf, 5. 20240812_TO 3 WTP Condition Assessment_Executed.pdf, 6. 20240812_TO 4 WWTP Condition Assessment_Executed.pdf, 7. 20240528_TO 5 Cityworks Support (1).pdf, 8. R-2023-251 Jacobs Consulting Services Agreement.pdf
Title
A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute An Authorization To Proceed For Work Order Number Jeg 24-02 With Jacobs Engineering, Inc. For Asset Management Consulting Services In An Amount Up To $901,000.00.

Strategic Plan Focus
Infrastructure & Facilities


Body

Staff Recommends: Approval of the attached Resolution.


Explanation:
The City of Hollywood Department of Public Utilities (DPU), operates and maintains critical infrastructure including the Southern Regional Wastewater Treatment Plant, the Water Treatment Plant, water distribution systems, sewer collection and transmission lines, reuse water supply networks, and stormwater management systems. These essential assets will benefit from a standardized approach to establish and maintain an organized and efficient Maintenance and Reliability program. The current system lacks this standardization, making it difficult to efficiently assess asset conditions, plan for necessary maintenance, and schedule necessary replacements.

To address these challenges, the DPU recommends engaging Jacobs Engineering Group, Inc. (Jacobs) to provide comprehensive asset management consultancy services. This engagement will involve a multi-pronged approach:

Asset Inventory and Condition Assessment:
Jacobs will conduct a thorough inventory of critical assets at the Water and Wastewater Treatment Plant's. This inventory will document the location, function, and current condition of each asset.

Lift Station Assessments:
Jacobs will assess the condition of select DPU lift stations.

Maintenance and Reliability Program Review:
Jacobs will evaluate the existing against established ISO 55001 standards to identify areas for improvement and ensure alignment with industry best practices.

CAMRA+ Methodology:
Jacobs will utilize the CAMRA+ (Critical Asset Management Review and Assessment) methodology. This structured approach ...

Click here for full text