Title: A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute An Authorization To Proceed For Work Order Number H&S 22-02 With Hazen And Sawyer, P.C., To Provide Professional Engineering Services Related To The Design Of Mechanical Integrity Testing And Operating Permit Renewal For Deep Injection Wells No. 1 And No.2, And Facility Permit Renewal For The Southern Regional Wastewater Treatment Plant In An Amount Not To Exceed $95,148.00.
Attachments: 1. Resolution - HS 22-02 Injection Well MIT Permit Renewal.pdf, 2. ATP- H&S 22-02 Injection Well MIT & Permit Renewal.pdf, 3. Proposal - H&S 22-02 Injection Well MIT & Permit Renewal.pdf, 4. Agreement Renewal - H&S 22-02 Injection Well MIT & Permit Renewal .pdf, 5. TermSheetATPHazenSawyerDeepInjectionWelFDEPRenewalPermitdoc.pdf
Title
A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute An Authorization To Proceed For Work Order Number H&S 22-02 With Hazen And Sawyer, P.C., To Provide Professional Engineering Services Related To The Design Of Mechanical Integrity Testing And Operating Permit Renewal For Deep Injection Wells No. 1 And No.2, And Facility Permit Renewal For The Southern Regional Wastewater Treatment Plant In An Amount Not To Exceed $95,148.00.


Strategic Plan Focus
Infrastructure & Facilites


Body

Staff Recommends: Approval of the attached Resolution.


Explanation:
The Southern Regional Wastewater Treatment Plant ("SRWWTP") is a 55.5 million gallon per day wastewater treatment facility that uses multiple treatment processes to treat wastewater and produces high quality effluent that is currently discharged into the Atlantic Ocean or the two existing Deep Injection Wells No. 1 and 2. These two wells were placed in service in 2002 and are currently serving as the primary disposal method at the SRWWTP under Florida Department of Environmental Protection ("FDEP") Permit Number 156419-009-007-UO/1M issued on February 15, 2018. This permit requires that the five-year mechanical integrity testing program be completed before August 21, 2022 for Deep Injection Well No. 1 and before August 31, 2022 for Deep Injection Well No. 2. The Department of Public Utilities ("Department") is also required to prepare and submit the operating permit renewal application for these two deep injection wells to FDEP before February 15, 2023, the expiration date of the permit.

The FDEP Domestic Wastewater Facility Permit Number FL0026255-25 for the operation of the SRWWTP will expire on August 29, 2022 and the operating permit is required to be renewed prior to the expiration date.

On September 20, 2017, the City Commission passed and adopted Resolution No. R-2017-283 which authorized the execution of cont...