File #: R-2023-211    Version: 1 Name: McKinley ST Interceptor Ventilation & Tyler ST Conflict Box Revision Project
Type: Resolution Status: Passed
File created: 6/15/2023 In control: Department of Public Utilities
On agenda: 7/5/2023 Final action: 7/5/2023
Title: A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute A Contract With Southeastern Engineering Contractors, Inc. In An Amount Up To $200,495.00 For Construction Services Related To The McKinley Street Interceptor Ventilation And Tyler Street Conflict Box Revision Project.
Attachments: 1. Resolution - McKinley ST Interceptor Ventilation & Tyler ST Conflict Box.pdf, 2. Contract - McKinley ST Interceptor Ventilation & Tyler ST Conflict Box.pdf, 3. Contract Book - McKinley ST Interceptor Ventilation & Tyler ST Conflict Box.pdf, 4. Bid Proposal – McKinley ST Interceptor Ventilation & Tyler ST Conflict Box.pdf, 5. Bid Tabulation - McKinley ST Interceptor Ventilation & Tyler ST Conflict Box.pdf, 6. Award Recommendation Letter - McKinley Street Interceptor Ventilation.pdf, 7. Presentation - McKinley Street Interceptor Ventilation and Tyler Street.pdf, 8. Sunbiz - McKinley ST Interceptor Ventilation & Tyler ST Conflict Box.pdf, 9. 2023-490 Term Sheet Southeastern Engineering.pdf

Title

A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute A Contract With Southeastern Engineering Contractors, Inc. In An Amount Up To $200,495.00 For Construction Services Related To The McKinley Street Interceptor Ventilation And Tyler Street Conflict Box Revision Project.

 

Strategic Plan Focus

Infrastructure & Facilities

 

 

Body

 

Staff Recommends:  Approval of the attached Resolution.

 

 

Explanation:

The City has the responsibility of planning, regulating, designing, constructing, operating, and maintaining the Southern Regional Wastewater Treatment Plant and the wastewater collection system including 85 sewer lift stations and over 280 miles of sewer conveyance.  Various locations within the sewer collection system, including the intersection of Tyler Street and 13th Avenue, and McKinley Street between 18th Avenue and N. 24th Avenue, have experienced a lack of air ventilation resulting in odor complaints from residents.  The Department of Public Utilities (“Department”) recommended addressing these concerns by installing vent pipes to provide ventilation & odor control at the aforementioned locations.  Should these measures prove successful, they may be replicated at other locations as needed.

 

Department staff prepared bid documents and posted a Notice of Bid Availability for Bid No. IFB-057-23-JJ on OpenGov in accordance with Section 38.43(A) of the Procurement Code on March 2, 2023.  Bid No. IFB-057-23-JJ was electronically opened on April 26, 2023, with the following results:

 

Bidder                                          Bid Total                                                               

1.                     Southeastern Engineering Contractors, Inc.                                          $200,495.00

 

Department and Office of Procurement staff thoroughly evaluated the submitted bid in accordance with Section 38.43(F) of the City’s Procurement Code, and after the evaluation, Southeastern Engineering Contractors, Inc. was determined to be the lowest responsive and responsible bidder.  On May 17, 2023, a Notice of Intent to Award related to the project was posted on the City’s website and on OpenGov, and resulted in no bid protests.

 

This agenda item seeks the City Commission’s approval and authorization for the appropriate City officials to execute the attached contract with Southeastern Engineering Contractors, Inc. in an amount up to $200,495.00 for the McKinley Street Interceptor Ventilation and Tyler Street Conflict Box Revision Project construction services.

 

Upon authorization from the City Commission, the project will be completed in 300 days from the date of the Authorization to Proceed.

 

 

Fiscal Impact

Funding for the project was included in the amended FY 2023 Capital Improvement Plan and is available in account number 442.409903.53600.563010.001482.000.000.

 

Department staff will manage this project.  No additional staff is needed as a result of this project.

 

 

Recommended for inclusion on the agenda by:

Feng (“Jeff”) Jiang, Assistant Director, Department of Public Utilities

Vincent Morello, Director, Department of Public Utilities

Gus Zambrano, Assistant City Manager/Sustainable Development

 

Attachments

                     Resolution - McKinley Street Interceptor Ventilation and Tyler Street Conflict Box Revision

                     Contract - McKinley Street Interceptor Ventilation and Tyler Street Conflict Box Revision

                     Contract Book - McKinley Street Interceptor Ventilation and Tyler Street Conflict Box Revision

                     Bid Proposal - Southeastern Engineering Contractors, Inc. - McKinley Street Interceptor Ventilation and Tyler Street Conflict Box Revision

                     Bid Tabulation - McKinley Street Interceptor Ventilation and Tyler Street Conflict Box Revision

                     Award Recommendation Letter - McKinley Street Interceptor Ventilation and Tyler Street Conflict Box Revision

                     Presentation - McKinley Street Interceptor Ventilation and Tyler Street Conflict Box Revision

                     Sunbiz Detail - McKinley Street Interceptor Ventilation and Tyler Street Conflict Box Revision