A Resolution Of The City Commission Of The City Of Hollywood, Florida, Ranking Professional Engineering Firms To Provide Professional Engineering Services Related To Design And Construction Administration Services For Hollywood Beach Utility Improvements; Authorizing The Appropriate City Officials To Negotiate An Agreement With Tetra Tech, Inc., The Highest Ranked Firm, For Consideration By The City Commission At A Later Date.
Strategic Plan Focus
Infrastructure & Facilities
Body
Staff Recommends: Approval of the attached Resolution.
Explanation:
The 2007 Water System Master Plan identified the need to replace aging water distribution system pipes throughout the City. In order to address the findings of the 2007 Water System Master Plan, the Department of Public Utilities developed a City-wide Water Main Replacement Program, which is currently being implemented. The Water Main Replacement Program prioritizes the replacement of the water mains based on the age and material of the pipelines and pipeline breaks rate in an area.
Hollywood Beach includes the North Beach and the South Central Beach neighborhoods. The water mains in the North Beach Neighborhood and South Central Neighborhood (along A1A) were installed between 1940 and 1968 and have reached their useful life and need to be replaced. Additionally, the Department has identified the need to upsize/retrofit existing sanitary sewer, force main and lift station infrastructure in the Hollywood Beach Area. Refer to Exhibit A for project area map.
The scope of services for the design and construction services for the Hollywood Beach Utility Improvements includes the following tasks:
• Topographic survey
• Environmental survey
• Utilities verification
• Subsurface utility evaluation
• Geotechnical investigation
• Design, including Tech Memo, 90% design submitted and complete bid package design
• Engineer’s estimate of construction cost
• Permitting
• Preparation of bidding documents and bidding assistance
• Construction administration services, including SFR compliance assistance
The Department of Public Utilities (“Department”) desires to retain a professional Engineering firm to provide engineering services for the design and construction administration services for Hollywood Beach Utility Improvements.
On March 19, 2020, the Department advertised for statement of qualifications for the Hollywood Beach Utility Improvements project in accordance with the procedures set forth in Section 287.055, Florida Statutes entitled “Consultants’ Competitive Negotiation Act” (“CCNA”) and the City’s Procurement Code.
On July 6, 2020, the Office of the City Clerk and the Department received statement of qualification packages from the following nine professional engineering firms:
1. BCC Engineering, LLC.
2. Chen Moore and Associates, Inc.
3. Craven Thompson & Associates, Inc.
4. Gannett Fleming, Inc.
5. Keith and Associates, Inc.
6. Kimley Horn and Associates, Inc.
7. M&J Engineering, P.C.
8. Miller Legg & Associates, Inc.
9. Tetra Tech, Inc.
The Department assembled a selection committee comprised of the following City staff: Feng Jiang, P.E., Vernal Sibble, P.E., Juan Figueroa, P.E, Clarissa Ip, P.E., and Wilhelmina Montero P.E.
On August 20, 2020, members of the selection committee met for the first time to evaluate the statement of qualification packages and the selection committee short-listed four firms for oral interviews.
On September 10, 2020, members of the selection committee conducted oral interviews with the four short-listed firms. The selection committee completed the evaluation process and ranked the firms based upon the stipulated guidelines/criteria in the statement of qualifications package as follows:
COMPANY |
TOTAL POINTS |
RANKING |
Tetra Tech, Inc. |
909 |
1st |
Kimley Horn and Associates, Inc. |
878 |
2nd |
Craven Thompson & Associates, Inc. |
871 |
3rd |
Chen Moore and Associates, Inc. |
866 |
4th |
The Department of Public Utilities staff will manage this project. No additional staff is needed as a result of this project.
Fiscal Impact
Approval of this resolution will not fiscally impact the City. The negotiated agreement will be brought back for Commission approval and the fiscal impact will be determined at that time.
Recommended for inclusion on the agenda by:
Clece Aurelus, Engineering Support Services Manager, Department of Public Utilities
Vivek Galav, Director, Department of Public Utilities
Gus Zambrano, Assistant City Manager/Sustainable Development
Attachments
01 Resolution - Hollywood Beach Utility Improvements
02 RFQ Final Ranking Results - Hollywood Beach Utility Improvements
03 Tetra Tech, Inc. RFQ - Hollywood Beach Utility Improvements
04 Kimley Horn and Associates, Inc. RFQ - Hollywood Beach Utility Improvements
05 Craven Thompson & Associates, Inc. RFQ - Hollywood Beach Utility Improvements
06 Chen Moore and Associates, Inc. RFQ - Hollywood Beach Utility Improvements
07 Gannett Fleming, Inc. RFQ - Hollywood Beach Utility Improvements
08 Keith & Associates, Inc. RFQ - Hollywood Beach Utility Improvements
09 M&J Engineering P.C. RFQ - Hollywood Beach Utility Improvements
10 Miller Legg & Associates, Inc. RFQ - Hollywood Beach Utility Improvements
11 BCC Engineering, LLC RFQ - Hollywood Beach Utility Improvements
12 Exhibit A Project Area Map - Hollywood Beach Utility Improvements