A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute An Authorization To Proceed For Work Order Number ARC 25-05 With Arcadis U.S., Inc. To Provide Professional Engineering Services Related To The Design, Permitting, And Bidding For The Conversion Of The Southern Regional Wastewater Treatment Plant Disinfection System From Chlorine Gas To Sodium Hypochlorite In An Amount Up To $494,305.00.
Strategic Plan Focus
Infrastructure & Facilities
Body
Staff Recommends: Approval of the attached Resolution.
Explanation:
The Southern Regional Wastewater Treatment Plant (“SRWWTP”) currently uses a chlorine gas disinfection system as the final step in the sewage treatment process prior to disposal. Department of Public Utilities (“Department”) staff have decided to replace the chlorine gas system with a hypochlorite system within the existing chlorine building.
On August 30, 2023, the City Commission passed and adopted Resolution No. R-2023-251, which authorized the execution of continuing professional consulting engineering services agreements with five firms for Water Treatment Plant and SRWWTP Projects, one of the firms being Arcadis U.S., Inc. (“ARC”).
Department staff requested a proposal to provide professional engineering services for the design, permitting, and bidding of the Conversion from Chlorine Gas to Sodium Hypochlorite System Project. ARC submitted a proposal in an amount up to $494,305.00. Department staff reviewed the proposal, including the project scope and fees in an amount up to $494,305.00, and determined that the scope and fees are fair, reasonable, and in accordance with industry standards.
This agenda item seeks the City Commission’s approval and authorization for the appropriate City officials to execute an Authorization to Proceed for Work Order No. ARC 25-05 with ARC to provide professional engineering services in an amount up to $494,305.00.
Upon authorization from the City Commission, the project is estimated to be completed within ten months from the Authorization to Proceed date.
Fiscal Impact:
Funding for this project was included in the amended FY 2025 Capital Improvement Plan and is available in account number 442.409903.53600.563013.001919.000.000.
Department staff will manage this project. No additional staff are needed as a result of this project.
Recommended for inclusion on the agenda by:
Feng (“Jeff”) Jiang, Assistant Director, Department of Public Utilities
Vincent Morello, Director, Department of Public Utilities
Chris O’Brien, Director of Public Safety