File #: R-2025-449    Version: Name: ATP H&S 26-01 Wastewater Master Plan Update - Phase 3
Type: Resolution Status: Agenda Ready
File created: 11/4/2025 In control: Department of Public Utilities
On agenda: 12/10/2025 Final action:
Title: A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute An Authorization To Proceed For Work Order Number H&S 26-01 With Hazen And Sawyer, P.C. To Provide Professional Engineering Services Related To Wastewater Master Plan Update - Phase 3, In An Amount Up To $95,000.00.
Attachments: 1. Resolution - ATP H&S 26-01 Wastewater Master Plan Phase 3 (LEGAL), 2. ATP - H&S 26-01 -Wastewater Master Plan Update - Phase 3, 3. Proposal - Wastewater Master Plan Phase 3, 4. Consulting Agreement 1324A - Hazen and Sawyer PC, 5. R-2023-251 Engineering Services Related to Water and Wastewater Treatment Plant Projects
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute An Authorization To Proceed For Work Order Number H&S 26-01 With Hazen And Sawyer, P.C. To Provide Professional Engineering Services Related To Wastewater Master Plan Update - Phase 3, In An Amount Up To $95,000.00.

 

Strategic Plan Focus

Infrastructure & Facilites

 

 

Body

 

Staff Recommends:  Approval of the attached Resolution.

 

 

Explanation:

The City operates the Wastewater System, which consists of a wastewater collection/transmission system, 86 sewer lift stations, the reuse supply system within the City’s corporate limits, and the Southern Regional Wastewater Treatment Plant.  The Department of Public Utilities (“Department”) has the responsibility for planning, regulating, designing, constructing, operating, and maintaining this wastewater system.  An updated Wastewater Master Plan is necessary to most effectively fulfill the City’s responsibilities, comply with regulatory programs at various levels (federal, state, county, and local), provide a high level of service to its residents, accommodate growth and economic development, and protect public health, safety, and the environment.

 

On April 20, 2022, pursuant to Resolution No. R-2022-115, the City Commission approved and authorized the execution of the professional engineering services agreement with Hazen and Sawyer, P.C. (“H&S”) to update the Wastewater Master Plan - Phase 2 in the amount of $1,804,858.00 with an understanding that Phase 3 would be presented to the City Commission for approval in FY 2026 in the amount of $95,000.00.

 

Phase 2 of the Wastewater Master Plan Update is complete; the Department needs to proceed to Phase 3.  Phase 3 involves assessing system vulnerability and criticality, implementing a capital improvements program, providing workshop assistance, and addressing regulatory considerations.

 

This agenda item seeks the City Commission’s approval and authorization to execute an Authorization to Proceed (“ATP”) for Work Order Number H&S 26-01 for Wastewater Master Plan Update - Phase 3 in an amount up to $95,000.00, based upon the project scope and fees, and the terms and conditions of the current professional engineering services agreement for the project.

 

Upon authorization from the City Commission, the project is expected to be completed within approximately 12 months from the date of execution of the Authorization to Proceed.

 

 

Fiscal Impact:

Funding for this project was included in the amended FY 2026 Capital Improvement Plan and is available in account number 442.409901.53600.531300.000731.000.000.

 

Department staff will manage this project.  No additional staff are needed as a result of this resolution.

 

 

Recommended for inclusion on the agenda by:

Vincent Morello, Director, Public Utilities

Chris O’Brien, Director, Public Safety