Title: A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving The Final Ranking For Construction Engineering Inspection Services And Authorizing The Appropriate City Officials To Negotiate A Contract With The Highest-Ranked Firm, R.J. Behar & Company, Inc., For The Construction Engineering Inspection Services For The Hollywood Beach Heights And Hollywood Country Estates Sidewalk, ADA Compliance And North 58th Avenue Sharrow Bike Lane Project.
Attachments: 1. Resolution CEI Consultant Ranking Beach HeightsPL .pdf, 2. RFQ-140-24-WV CEI Services for Hollywood Beach Heights and Hollywood Beach Estates Sidewalk Network.pdf, 3. AE_Engineering,_Inc._-_RFQ-140-24-WV.pdf, 4. Beach Heights Construction & CEI LAP Agreement.pdf, 5. CEI_Services_for_Hollywood_Beach_Heights_+_Hollywod_Beach_Estates_Sidewalk_Network.pdf, 6. JMT Proposal_RFQ-140-24-WV_Hollywood_Beach_Heights_and_Estates_Sidwalk_Network.pdf, 7. Evaluation Tabulation (RFQ-140-24-WV).pdf, 8. Notice of Intent to Award (RFQ-140-24-WV) .pdf, 9. R-2017-323.pdf, 10. R-2022-104.pdf, 11. R-2022-354.pdf, 12. R-2024-006.pdf

Title

A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving The Final Ranking For Construction Engineering Inspection Services And Authorizing The Appropriate City Officials To Negotiate A Contract With The Highest-Ranked Firm, R.J. Behar & Company, Inc., For The Construction Engineering Inspection Services For The Hollywood Beach Heights And Hollywood Country Estates Sidewalk, ADA Compliance And North 58th Avenue Sharrow Bike Lane Project.

 

Strategic Plan Focus

Infrastructure & Facilities

 

 

Body

 

Staff Recommends: Approval of the attached Resolution.

 

 

Explanation:

The City of Hollywood seeks to complete the Citywide sidewalk network to improve pedestrian safety and alternative modes of transportation. Grant funding for new sidewalk construction can be secured under the Broward County Planning Organization Complete Streets and other Localized Initiatives Program.

 

On November 1, 2017, the City Commission approved Resolution R-2017-323, supporting the Complete Streets and other Localized Initiatives Program (“CSLIP”) grant application to the Broward Metropolitan Planning Organization (“MPO”) for the Hollywood Beach Heights and Hollywood Country Estates Sidewalk, ADA, and N. 58th Avenue Sharrow Installation Project.

 

The Broward MPO issued an award letter for the projects dated January 22, 2019, which was included in the Florida Department of Transportation (“FDOT”) five-year work program for construction in FY-2024.

 

On April 20, 2022, the City Commission passed and adopted Resolution No. R-2022-104, approving and authorizing the appropriate City officials to execute Local Agency Program (“LAP”) Agreements in order to receive reimbursement funds for the design of the Beverly Park Sidewalk Project.

 

After conducting consultant selection, on December 7, 2022, the City Commission passed and adopted Resolution No. R-2022-354 approving and authorizing appropriate City officials to execute a Professional Services Agreement with Kimley Horn and Associates, Inc. (“KHA”) for the design and permitting of the Hollywood Beach Heights and Hollywood Country Estates Sidewalk, ADA, and N. 58th Avenue Sharrow Installation Project in an amount up to $427,339.00.

 

The project design has been completed, construction documents have been reviewed and approved by FDOT for construction phase funding.

 

On January 17, 2024, the City Commission passed and adopted Resolution No. 2024-006, approving and authorizing the appropriate City officials to accept and execute Hollywood Beach Heights and Hollywood Country Estates Sidewalk, ADA, and N. 58th Avenue Sharrow Installation Project LAP Grant Agreements for construction and construction engineering inspection in the amounts of $2,690,339.00 and $354.740.00.

 

City staff followed the requirements set forth in Section 287.055 Florida Statutes, entitled “Consultants Competitive Negotiation Act” (“CCNA”) and the City’s Procurement Code to obtain the services of Construction Engineering Inspection engineering consultants for this project. On October 26, 2023, the City advertised, on www.OpenGov.com <http://www.OpenGov.com> Request for Qualifications No. RFQ- 140-24-WV for Construction Engineering Inspection Services for Hollywood Beach Heights and Hollywood Country Estates Sidewalk, ADA, and N. 58th Avenue Sharrow Installation Project.

 

On November 16, 2023, the Office of the City Clerk and the Department of Design and Construction Management (“DCM”) received Statement of Qualifications packages from the following four firms:

 

                     AE Engineering, Inc.

                     Johnson, Mirmiran & Thompson

                     RJ Behar & Company, Inc.

 

A Selection Committee was assembled, approved by and working under the guidance of the Office of Procurement and Contract Compliance, and made up of a Project Manager from the Public Utilities Department, as well as a Construction Management Field Services Manager and an Engineering Support Services Manager from DCM. On November 28, 2023, the Selection Committee met in a publicly advertised meeting to evaluate Statements of Qualifications based on the selection criteria published in the RFQ.

 

The Selection Committee completed the selection evaluation ranking the firms as follows (ranked in order starting with the most qualified firm):

 

1.                     R. J. Behar & Company, Inc.

2.                     Johnson, Mirmiran & Thompson. Inc.

3.                     AE Engineering, Inc.

 

A Notice of Intent to Award was posted on November 28, 2023, and no protests were received. The Department of Design and Construction Management recommends that the City Commission approve the final rankings and authorize the appropriate City officials to negotiate a contract with the highest ranked firm for this project.

 

Upon negotiating a contract with the highest-ranked firm, if the contract amount falls within the City Manager’s authority pursuant to Section 38.38 of the City’s Procurement Code, the City Manager will execute the contract; however, if the contract amount exceeds the City Manager’s authority, the contract will be brought back to the City Commission for consideration at a later date.

 

 

Fiscal Impact:

Contingency funding for this project was included in the amended FY 2024 Capital Improvement Plan and is available in account number 117.179901.51900.563010.001463.000.000.

 

 

Recommended for inclusion on the agenda by:

Jose Cortes, Director, Department of Design and Construction Services.

Gus Zambrano, AICP, Assistant City Manager/Sustainable Development