File #: R-2023-324    Version: 1 Name: Johnson Street Bridge Widening
Type: Resolution Status: Passed
File created: 9/19/2023 In control: Engineering Division
On agenda: 10/18/2023 Final action: 10/18/2023
Title: A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute An Authorization To Proceed With The Corradino Group, Inc. For Professional Consulting Services For The Preparation Of The Final Design, Permitting, And Construction Specifications For The Replacement And Widening Of The Johnson Street Bridge For A Total Amount Not To Exceed $589,008.78.
Attachments: 1. Resolution.pdf, 2. ATP #1 Corradino Group.pdf, 3. ATP #2 Corradino Group.pdf, 4. R-2021-208.pdf, 5. The Corradino Group,Inc. Professional CSA.pdf, 6. Scope of Services Task Work Order Proposal - Johnson Street Bridge Replacement.pdf, 7. The Corradino Group Inc - City of Hollywood - COI.pdf

Title

A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute An Authorization To Proceed With The Corradino Group, Inc. For Professional Consulting Services For The Preparation Of The Final Design, Permitting, And Construction Specifications For The Replacement And Widening Of The Johnson Street Bridge For A Total Amount Not To Exceed $589,008.78.

 

Strategic Plan Focus

Quality of Life & Strong Neighborhoods

 

 

Body

 

Staff Recommends:  Approval of the attached Resolution.

 

 

Explanation:

The FDOT Bridge inspection report dated February 10, 2021, for the Johnson Street Bridge over the C-10 canal, located between North 30th Road and North 31st Avenue (by Bravo) determined the bridge was functionally obsolete.

 

On February 21, 2023, the Department of Development Services, Engineering, Transportation and Mobility Division issued an Authorization to Proceed (ATP-01) in the amount of $33,899.30 to the Corradino Group, Inc., (CG) to conduct a feasibility study and develop a conceptual design to widen the Johnson Street Bridge and address the obsolete functionality.

 

The results of the feasibility study indicated that due the limited design life of the existing structures, a complete replacement of the bridge was necessary in order to widen the bridge.

 

The Department of Development Services, Engineering, Transportation and Mobility Division staff negotiated a proposal with CG for professional roadway and bridge design services to complete the final engineering design, permitting, and construction specifications to replace and widen the Johnson Street bridge in an amount not to exceed $589,008.78.

 

 

Fiscal Impact:

Funding for this phase of the project was included in the amended FY 2024 Capital Improvement Plan and is available in account number 334.149901.54100.563010.001687.000.000.

 

 

Recommended for inclusion on the agenda by:

Azita Behmardi, P.E. Deputy Director of Development Services

Andria Wingett, Interim Director of Development Services

Gus Zambrano, AICP, Assistant City Manager/Sustainable Development