File #: R-2025-199    Version: 1 Name: Hollywood Police HQ FPL Easements
Type: Resolution Status: Agenda Ready
File created: 5/6/2025 In control: Engineering Division
On agenda: 6/18/2025 Final action:
Title: A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute Three Easement Agreements With Florida Power & Light Company For The Purpose Of Installing And Maintaining New Power Services Related To The New Police Headquarters Project, A General Obligation Bond Project; And To Execute One Right-Of-Way Easement.
Attachments: 1. Resolution Police HQ FPL Easement rev.pdf, 2. Exhibit 1 FPL easements within new PD parcel.pdf, 3. Exhibit 2 FPL easements north of new PD parcel.pdf, 4. Exhibit 3 FPL Easement forms.pdf, 5. Exhibit 4 ROW Easement sketch and legal.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

A Resolution Of The City Commission Of The City Of Hollywood, Florida, Approving And Authorizing The Appropriate City Officials To Execute Three Easement Agreements With Florida Power & Light Company For The Purpose Of Installing And Maintaining New Power Services Related To The New Police Headquarters Project, A General Obligation Bond Project; And To Execute One Right-Of-Way Easement.  

 

Strategic Plan Focus

Infrastructure & Facilities

 

 

Body

 

Staff Recommends: Approval of the attached Resolution.

 

 

Explanation:

In a Special Election held on March 12, 2019, voters of the City approved a variety of projects to be funded by a General Obligation Bond, including the new Hollywood Police Headquarters project.  On May 1, 2024, the City Commission passed and adopted Resolution No. R-2024-149, authorizing the appropriate City officials to execute a Phase II Construction Services Agreement with Moss & Associates, LLC. 

 

The New Police Headquarters project is now in the Construction phase and requires power services be provided to the new police headquarters building and garage. 

 

Florida Power & Light Company (“FPL”) has completed the design of the electrical transmission and distributions lines required for the project. To serve the new police headquarters facility, three easements will be necessary for FPL to construct, operate, and maintain this infrastructure. Of the three easements, two are located within the new police headquarters parcel located at 401 South Park Road and one is located near and outside of the new police headquarters parcel’s northwest corner, within City owned land to the north.

 

Below are general locations of the proposed FPL easements within the new police headquarters parcel, attached as Exhibit “1”:

                     Along the public access road north of the new Police Headquarters building.

                     Along the service road located south of the new Police Headquarters garage.

 

Below is general location of the proposed FPL easement outside of the new police headquarters parcel within city owned land to the north, attached as Exhibit “2”:

 

                     At the northwest corner of the intersection of the public access road and South Park Road.

                     

In support of the new Police Headquarters project, the City desires to grant the three above-mentioned easements to FPL. The attached Exhibit “3” contains the required Easement forms, one for each location, and the respective sketch and legal descriptions.

 

In addition, a new Right-of-Way Easement is necessary along South Park Road from Hollywood Boulevard to south of South Luna Court to accommodate the existing roadway and related utilities currently within this area, attached as Exhibit “4”. Granting this easement will accommodate existing roadways and utilities within the area as well as any future right-of-way related features.

 

 

Fiscal Impact:

Approval of this resolution will not fiscally impact the City as this is a proposal to execute three easement agreements.

 

 

Recommended for inclusion on the agenda by:

Clarissa Ip, PE, City Engineer

Andria Wingett, Director of Development Services

Raelin Storey, Assistant City Manager